Tavora Residences By Jhk Heights Real Estate Development construction progress
The registered completion date for Tavora Residences By Jhk Heights Real Estate Development in International City Phase 3 is December 2026. At the last site inspection, in October 2026, it was 86% built. The developer is Jhk Heights Real Estate Development.
86%
Built, at the site inspection of 15 October 2026
On pace for its date
- Registered completion date
- December 2026
- Finish at recent pace
- January 2027
- Construction started
- September 2024
- First registered
- August 2025
- Developer
- Jhk Heights Real Estate Development
- Community
- International City Phase 3
- Units
- 95
- Escrow bank
- United Bank Limited
- Name in Arabic
- تافورا ريزيدنسز باي جيه إتش كيه هايتس للتطوير العقاري
- Project number
- 3825
- Site inspections
- 4
Schedule
Since November 2025 Tavora Residences By Jhk Heights Real Estate Development has added about 4.0 points a month. That puts 100% around January 2027, within three months of its registered completion date of December 2026.
Site inspections
15 October 2026
86%+25 pts
12 May 2026
61%+19 pts
17 November 2025
42%+14 pts
7 July 2025
28%
Context
International City Phase 3 has 20 projects under construction, 28% built on average.
Own a unit in Tavora Residences By Jhk Heights Real Estate Development?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Tavora Residences By Jhk Heights Real Estate Development handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Tavora Residences By Jhk Heights Real Estate Development?
- Tavora Residences By Jhk Heights Real Estate Development was 86% built at the site inspection on 15 October 2026. The site has been inspected 4 times since July 2025. The Land Department took 28 site photos at its inspections.
- Is Tavora Residences By Jhk Heights Real Estate Development delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
- Who is building Tavora Residences By Jhk Heights Real Estate Development?
- The registered developer is Jhk Heights Real Estate Development.
- Which bank holds the escrow account for Tavora Residences By Jhk Heights Real Estate Development?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Maiden ResidenceNearby in International City Phase 3. 73%, Due December 2025, passed.
- Linden ResidencesNearby in International City Phase 3. 27%, Due December 2027.
- Moonsa Residences 2Nearby in International City Phase 3. 1.0%, Due December 2026.
- Mayflower ResidencesNearby in International City Phase 3. 96%, Due March 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.