Elevia Residences construction progress

The registered completion date for Elevia Residences in International City Phase 3 is June 2027. At the last site inspection, in October 2026, it was 9.2% built. The developer is Valores Property Development.

9.2%

Built, at the site inspection of 19 October 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
September 2033
Construction started
August 2025
First registered
July 2025
Developer
Valores Property Development
Units
106
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
ايليفيا رزيدينسيز
Project number
3635
Site inspections
3

Schedule

Between April 2026 and October 2026 the site added about 1.1 points a month. At that rate it would finish around September 2033, more than three months after its registered date of June 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 October 2026

9.2%+6.2 pts

  • Elevia Residences construction site, inspection photo 1, 19 October 2026
  • Elevia Residences construction site, inspection photo 2, 19 October 2026
  • Elevia Residences construction site, inspection photo 3, 19 October 2026
  • Elevia Residences construction site, inspection photo 4, 19 October 2026

30 April 2026

3.0%+3.0 pts

  • Elevia Residences construction site, inspection photo 1, 30 April 2026
  • Elevia Residences construction site, inspection photo 2, 30 April 2026
  • Elevia Residences construction site, inspection photo 3, 30 April 2026
  • Elevia Residences construction site, inspection photo 4, 30 April 2026

22 April 2025

0%

  • Elevia Residences construction site, inspection photo 1, 22 April 2025
  • Elevia Residences construction site, inspection photo 2, 22 April 2025

All 13 site photos, by inspection date

Context

International City Phase 3 has 20 projects under construction, 28% built on average.

Own a unit in Elevia Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Elevia Residences handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Elevia Residences?
Elevia Residences was 9.2% built at the site inspection on 19 October 2026. The site has been inspected 3 times since April 2025. The Land Department took 13 site photos at its inspections.
Is Elevia Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Elevia Residences?
The registered developer is Valores Property Development.
Which bank holds the escrow account for Elevia Residences?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.