Elevia Residences III construction progress
The registered completion date for Elevia Residences III in International City Phase 3 is July 2027. At the last site inspection, in June 2026, it was 0% built. The developer is Valores Wbay Property Development.
0%
Built, at the site inspection of 22 June 2026
Running behind its date
- Registered completion date
- July 2027
- Finish at recent pace
- August 4270
- Construction started
- August 2025
- First registered
- September 2025
- Developer
- Valores Wbay Property Development
- Community
- International City Phase 3
- Units
- 105
- Escrow bank
- National Bank of Ras Al Khaimah
- Name in Arabic
- مساكن إيليفيا Iii
- Project number
- 3882
- Site inspections
- 2
Schedule
Between July 2025 and June 2026 the site added about 0.0 points a month. At that rate it would finish around August 4270, more than three months after its registered date of July 2027.
Site inspections
22 June 2026
0%+0.0 pts
29 July 2025
0%
Context
International City Phase 3 has 20 projects under construction, 28% built on average.
Own a unit in Elevia Residences III?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Elevia Residences III handover date?
- The registered completion date is July 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 4270. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Elevia Residences III?
- Elevia Residences III was 0% built at the site inspection on 22 June 2026. The site has been inspected 2 times since July 2025. The Land Department took 6 site photos at its inspections.
- Is Elevia Residences III delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
- Who is building Elevia Residences III?
- The registered developer is Valores Wbay Property Development.
- Which bank holds the escrow account for Elevia Residences III?
- National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Maiden ResidenceNearby in International City Phase 3. 73%, Due December 2025, passed.
- Linden ResidencesNearby in International City Phase 3. 27%, Due December 2027.
- Moonsa Residences 2Nearby in International City Phase 3. 1.0%, Due December 2026.
- Mayflower ResidencesNearby in International City Phase 3. 96%, Due March 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)