Nest construction progress
Nest in International City Phase 3 is 0.8% built at the Land Department inspection of May 2026. Developer Andi Real Estate Development. Completion registered for April 2027.
0.8%
Built, at the Land Department site inspection of 14 May 2026
Running behind its date
- Completion date (Land Department)
- April 2027
- Finish at recent pace
- January 2102
- Construction started
- September 2025
- Registered with the Land Department
- December 2025
- Developer
- Andi Real Estate Development
- Community
- International City Phase 3
- Units
- 112
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- نست
- Land Department project number
- 4112
- Land Department site inspections
- 2
Schedule
Between October 2025 and May 2026 the site added about 0.1 points a month. At that rate it would finish around January 2102, more than three months after the April 2027 date registered with the Land Department.
Site inspections
14 May 2026
0.8%+0.8 pts
6 October 2025
0%
Context
International City Phase 3 has 21 projects under construction, 30% built on average.
Own a unit in Nest?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Nest be completed?
- The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around January 2102. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Nest is built?
- 0.8%, measured at the Land Department site inspection on 14 May 2026. The Land Department engineers have inspected the site 2 times since October 2025.
- Is Nest delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
- Who is building Nest?
- The registered developer is Andi Real Estate Development.
- Which bank holds the escrow account for Nest?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Moonsa ResidencesNearby in International City Phase 3. 95%, Due August 2025, passed.
- The Maiden ResidenceNearby in International City Phase 3. 73%.
- Linden ResidencesNearby in International City Phase 3. 27%.
- Equiti TowerNearby in International City Phase 3. 70%, Due August 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.