Zyra Vista Residences construction progress

Zyra Vista Residences in International City Phase 3 is 2.1% built at the Land Department inspection of July 2026. Developer Laraix Developers. Completion registered for March 2027.

2.1%

Built, at the Land Department site inspection of 1 July 2026

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
February 2085
Construction started
April 2025
Registered with the Land Department
April 2025
Developer
Laraix Developers
Units
51
Escrow bank
United Bank Limited
Name in Arabic
سييرا فيستا رزيدينسيز
Land Department project number
3560
Land Department site inspections
2

Schedule

Between March 2025 and July 2026 the site added about 0.1 points a month. At that rate it would finish around February 2085, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 July 2026

2.1%+2.1 pts

  • Zyra Vista Residences construction site, Land Department inspection photo 1, 1 July 2026
  • Zyra Vista Residences construction site, Land Department inspection photo 2, 1 July 2026

24 March 2025

0%

  • Zyra Vista Residences construction site, Land Department inspection photo 1, 24 March 2025
  • Zyra Vista Residences construction site, Land Department inspection photo 2, 24 March 2025

All 4 site photos, by inspection date

Context

International City Phase 3 has 21 projects under construction, 30% built on average.

Laraix Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Zyra Vista Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Zyra Vista Residences be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around February 2085. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Zyra Vista Residences is built?
2.1%, measured at the Land Department site inspection on 1 July 2026. The Land Department engineers have inspected the site 2 times since March 2025.
Is Zyra Vista Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Zyra Vista Residences?
The registered developer is Laraix Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Zyra Vista Residences?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.