08 Life Residences construction progress
08 Life Residences in International City Phase 3 was registered to complete in May 2026 and is still under construction. At the last site inspection, in November 2026, it was 78% built. The developer is Deniz Properties.
78%
Built, at the site inspection of 10 November 2026
6 months past its registered completion date
- Registered completion date
- May 2026
- Finish at recent pace
- April 2027
- Construction started
- October 2024
- First registered
- April 2025
- Developer
- Deniz Properties
- Community
- International City Phase 3
- Units
- 107
- Escrow bank
- Emirates NBD
- Name in Arabic
- 08 لايف ريسيدنزس
- Project number
- 3590
- Site inspections
- 6
Schedule
08 Life Residences was registered to complete in May 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 4.0 points a month. Kept at that rate, the site would reach 100% around April 2027.
Site inspections
10 November 2026
78%+13 pts
26 August 2026
65%+17 pts
30 April 2026
48%+12 pts
22 December 2025
36%+12 pts
15 September 2025
24%+14 pts
25 March 2025
9.2%
Context
International City Phase 3 has 20 projects under construction, 28% built on average.
Deniz Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in 08 Life Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 08 Life Residences handover date?
- The registered completion date was May 2026, and the register still lists 08 Life Residences as under construction. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on 08 Life Residences?
- 08 Life Residences was 78% built at the site inspection on 10 November 2026. The site has been inspected 6 times since March 2025. The Land Department took 44 site photos at its inspections.
- Is 08 Life Residences delayed?
- Yes. Its registered completion date of May 2026 has passed and the project is still listed as under construction.
- Who is building 08 Life Residences?
- The registered developer is Deniz Properties. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for 08 Life Residences?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 09 Life ResidencesAlso by Deniz Properties. 6.8%, Due December 2027.
- The Maiden ResidenceNearby in International City Phase 3. 73%, Due December 2025, passed.
- Linden ResidencesNearby in International City Phase 3. 27%, Due December 2027.
- Moonsa Residences 2Nearby in International City Phase 3. 1.0%, Due December 2026.
- Mayflower ResidencesNearby in International City Phase 3. 96%, Due March 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)