08 Life Residences construction progress

08 Life Residences in International City Phase 3 was registered to complete in May 2026 and is still under construction. At the last site inspection, in November 2026, it was 78% built. The developer is Deniz Properties.

78%

Built, at the site inspection of 10 November 2026

6 months past its registered completion date

Registered completion date
May 2026
Finish at recent pace
April 2027
Construction started
October 2024
First registered
April 2025
Developer
Deniz Properties
Units
107
Escrow bank
Emirates NBD
Name in Arabic
08 لايف ريسيدنزس
Project number
3590
Site inspections
6

Schedule

08 Life Residences was registered to complete in May 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 4.0 points a month. Kept at that rate, the site would reach 100% around April 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 November 2026

78%+13 pts

  • 08 Life Residences construction site, inspection photo 1, 10 November 2026
  • 08 Life Residences construction site, inspection photo 2, 10 November 2026
  • 08 Life Residences construction site, inspection photo 3, 10 November 2026
  • 08 Life Residences construction site, inspection photo 4, 10 November 2026

26 August 2026

65%+17 pts

  • 08 Life Residences construction site, inspection photo 1, 26 August 2026
  • 08 Life Residences construction site, inspection photo 2, 26 August 2026
  • 08 Life Residences construction site, inspection photo 3, 26 August 2026
  • 08 Life Residences construction site, inspection photo 4, 26 August 2026

30 April 2026

48%+12 pts

  • 08 Life Residences construction site, inspection photo 1, 30 April 2026
  • 08 Life Residences construction site, inspection photo 2, 30 April 2026
  • 08 Life Residences construction site, inspection photo 3, 30 April 2026
  • 08 Life Residences construction site, inspection photo 4, 30 April 2026

22 December 2025

36%+12 pts

  • 08 Life Residences construction site, inspection photo 1, 22 December 2025
  • 08 Life Residences construction site, inspection photo 2, 22 December 2025
  • 08 Life Residences construction site, inspection photo 3, 22 December 2025
  • 08 Life Residences construction site, inspection photo 4, 22 December 2025

15 September 2025

24%+14 pts

  • 08 Life Residences construction site, inspection photo 1, 15 September 2025
  • 08 Life Residences construction site, inspection photo 2, 15 September 2025
  • 08 Life Residences construction site, inspection photo 3, 15 September 2025
  • 08 Life Residences construction site, inspection photo 4, 15 September 2025

25 March 2025

9.2%

  • 08 Life Residences construction site, inspection photo 1, 25 March 2025
  • 08 Life Residences construction site, inspection photo 2, 25 March 2025
  • 08 Life Residences construction site, inspection photo 3, 25 March 2025
  • 08 Life Residences construction site, inspection photo 4, 25 March 2025

All 44 site photos, by inspection date

Context

International City Phase 3 has 20 projects under construction, 28% built on average.

Deniz Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in 08 Life Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the 08 Life Residences handover date?
The registered completion date was May 2026, and the register still lists 08 Life Residences as under construction. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on 08 Life Residences?
08 Life Residences was 78% built at the site inspection on 10 November 2026. The site has been inspected 6 times since March 2025. The Land Department took 44 site photos at its inspections.
Is 08 Life Residences delayed?
Yes. Its registered completion date of May 2026 has passed and the project is still listed as under construction.
Who is building 08 Life Residences?
The registered developer is Deniz Properties. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for 08 Life Residences?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.