08 Life Residences construction progress
08 Life Residences in International City Phase 3 is 65% built at the Land Department inspection of August 2026. Developer Deniz Properties. Completion registered for May 2026.
65%
Built, at the Land Department site inspection of 26 August 2026
4 months past its registered completion date
- Completion date (Land Department)
- May 2026
- Finish at recent pace
- June 2027
- Construction started
- October 2024
- Registered with the Land Department
- April 2025
- Developer
- Deniz Properties
- Community
- International City Phase 3
- Units
- 107
- Escrow bank
- Emirates NBD
- Name in Arabic
- 08 لايف ريسيدنزس
- Land Department project number
- 3590
- Land Department site inspections
- 5
Schedule
08 Life Residences was registered to complete in May 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 3.6 points a month. Kept at that rate, the site would reach 100% around June 2027.
Site inspections
26 August 2026
65%+17 pts
30 April 2026
48%+12 pts
22 December 2025
36%+12 pts
15 September 2025
24%+14 pts
25 March 2025
9.2%
Context
International City Phase 3 has 21 projects under construction, 30% built on average.
Deniz Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in 08 Life Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will 08 Life Residences be completed?
- The completion date registered with the Dubai Land Department is May 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of 08 Life Residences is built?
- 65%, measured at the Land Department site inspection on 26 August 2026. The Land Department engineers have inspected the site 5 times since March 2025.
- Is 08 Life Residences delayed?
- Yes. Its registered completion date of May 2026 has passed and the Land Department still lists it as under construction.
- Who is building 08 Life Residences?
- The registered developer is Deniz Properties. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for 08 Life Residences?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 09 Life ResidencesAlso by Deniz Properties. 6.8%, Due December 2027.
- Moonsa ResidencesNearby in International City Phase 3. 95%, Due August 2025, passed.
- The Maiden ResidenceNearby in International City Phase 3. 73%.
- Linden ResidencesNearby in International City Phase 3. 27%.
- Equiti TowerNearby in International City Phase 3. 70%, Due August 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.










.jpeg&w=3840&q=75)