Chapter 02 construction progress
Chapter 02 in International City Phase 3 is 2.1% built at the site inspection of July 2026. Developer Newbury Chapter Real Estate Development. Completion registered for December 2028.
2.1%
Built, at the site inspection of 1 July 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- January 2072
- Construction started
- August 2025
- First registered
- November 2026
- Developer
- Newbury Chapter Real Estate Development
- Community
- International City Phase 3
- Units
- 94
- Escrow bank
- Al Ahli Bank of Kuwait
- Name in Arabic
- شابتر 02
- Project number
- 3841
- Site inspections
- 2
Schedule
Between July 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around January 2072, more than three months after its registered date of December 2028.
Site inspections
1 July 2026
2.1%+2.1 pts
9 July 2025
0%
Context
International City Phase 3 has 20 projects under construction, 26% built on average.
Own a unit in Chapter 02?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Chapter 02 be completed?
- The registered completion date is December 2028. At the pace of its recent inspections the site would reach 100% around January 2072. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- How much of Chapter 02 is built?
- 2.1%, measured at the site inspection on 1 July 2026. The site has been inspected 2 times since July 2025.
- Is Chapter 02 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Chapter 02?
- The registered developer is Newbury Chapter Real Estate Development.
- Which bank holds the escrow account for Chapter 02?
- Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Maiden ResidenceNearby in International City Phase 3. 73%, Due December 2025, passed.
- Linden ResidencesNearby in International City Phase 3. 27%, Due December 2027.
- Moonsa Residences 2Nearby in International City Phase 3. 1.0%, Due December 2026.
- Mayflower ResidencesNearby in International City Phase 3. 96%, Due March 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.