27 East End Garden Residences By Mirha Homes Real Estate Development construction progress

27 East End Garden Residences By Mirha Homes Real Estate Development in International City Phase 3 is 40% built at the Land Department inspection of August 2026. Developer Mirha Homes Real Estate Development. Completion registered for January 2027.

40%

Built, at the Land Department site inspection of 10 August 2026

Running behind its date

Completion date (Land Department)
January 2027
Finish at recent pace
November 2027
Construction started
February 2025
Registered with the Land Department
August 2025
Developer
Mirha Homes Real Estate Development
Units
96
Escrow bank
Mashreq Bank
Name in Arabic
إيست إند جاردن رسيدانس من ميرها هومز للتطوير العقاري 27
Land Department project number
3486
Land Department site inspections
4

Schedule

Between November 2025 and August 2026 the site added about 4.0 points a month. At that rate it would finish around November 2027, more than three months after the January 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

10 August 2026

40%+20 pts

  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 1, 10 August 2026
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 2, 10 August 2026
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 3, 10 August 2026
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 4, 10 August 2026

30 April 2026

20%+14 pts

  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 1, 30 April 2026
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 2, 30 April 2026
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 3, 30 April 2026
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 4, 30 April 2026

26 November 2025

6.4%+4.6 pts

  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 1, 26 November 2025
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 2, 26 November 2025
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 3, 26 November 2025
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 4, 26 November 2025

31 January 2025

1.9%

  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 1, 31 January 2025
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 2, 31 January 2025
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, Land Department inspection photo 3, 31 January 2025

All 20 site photos, by inspection date

Context

International City Phase 3 has 21 projects under construction, 30% built on average.

Own a unit in 27 East End Garden Residences By Mirha Homes Real Estate Development?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will 27 East End Garden Residences By Mirha Homes Real Estate Development be completed?
The completion date registered with the Dubai Land Department is January 2027. At the pace of its recent inspections the site would reach 100% around November 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of 27 East End Garden Residences By Mirha Homes Real Estate Development is built?
40%, measured at the Land Department site inspection on 10 August 2026. The Land Department engineers have inspected the site 4 times since January 2025.
Is 27 East End Garden Residences By Mirha Homes Real Estate Development delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
Who is building 27 East End Garden Residences By Mirha Homes Real Estate Development?
The registered developer is Mirha Homes Real Estate Development.
Which bank holds the escrow account for 27 East End Garden Residences By Mirha Homes Real Estate Development?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.