27 East End Garden Residences By Mirha Homes Real Estate Development construction progress

The registered completion date for 27 East End Garden Residences By Mirha Homes Real Estate Development in International City Phase 3 is January 2027. At the last site inspection, in August 2026, it was 40% built. The developer is Mirha Homes Real Estate Development.

58%

Built, at the site inspection of 10 August 2026

Running behind its date

Registered completion date
January 2027
Finish at recent pace
November 2027
Construction started
February 2025
First registered
August 2025
Developer
Mirha Homes Real Estate Development
Units
96
Escrow bank
Mashreq Bank
Name in Arabic
إيست إند جاردن رسيدانس من ميرها هومز للتطوير العقاري 27
Project number
3486
Site inspections
4

Schedule

Between November 2025 and August 2026 the site added about 4.0 points a month. At that rate it would finish around November 2027, more than three months after its registered date of January 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 August 2026

40%+20 pts

  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 1, 10 August 2026
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 2, 10 August 2026
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 3, 10 August 2026
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 4, 10 August 2026

30 April 2026

20%+14 pts

  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 1, 30 April 2026
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 2, 30 April 2026
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 3, 30 April 2026
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 4, 30 April 2026

26 November 2025

6.4%+4.6 pts

  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 1, 26 November 2025
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 2, 26 November 2025
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 3, 26 November 2025
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 4, 26 November 2025

31 January 2025

1.9%

  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 1, 31 January 2025
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 2, 31 January 2025
  • 27 East End Garden Residences By Mirha Homes Real Estate Development construction site, inspection photo 3, 31 January 2025

All 20 site photos, by inspection date

Context

International City Phase 3 has 20 projects under construction, 28% built on average.

Own a unit in 27 East End Garden Residences By Mirha Homes Real Estate Development?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the 27 East End Garden Residences By Mirha Homes Real Estate Development handover date?
The registered completion date is January 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on 27 East End Garden Residences By Mirha Homes Real Estate Development?
27 East End Garden Residences By Mirha Homes Real Estate Development was 58% built at the site inspection on 10 August 2026. The site has been inspected 4 times since January 2025. The Land Department took 20 site photos at its inspections.
Is 27 East End Garden Residences By Mirha Homes Real Estate Development delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
Who is building 27 East End Garden Residences By Mirha Homes Real Estate Development?
The registered developer is Mirha Homes Real Estate Development.
Which bank holds the escrow account for 27 East End Garden Residences By Mirha Homes Real Estate Development?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.