27 East End Garden Residences By Mirha Homes Real Estate Development construction progress
The registered completion date for 27 East End Garden Residences By Mirha Homes Real Estate Development in International City Phase 3 is January 2027. At the last site inspection, in August 2026, it was 40% built. The developer is Mirha Homes Real Estate Development.
58%
Built, at the site inspection of 10 August 2026
Running behind its date
- Registered completion date
- January 2027
- Finish at recent pace
- November 2027
- Construction started
- February 2025
- First registered
- August 2025
- Developer
- Mirha Homes Real Estate Development
- Community
- International City Phase 3
- Units
- 96
- Escrow bank
- Mashreq Bank
- Name in Arabic
- إيست إند جاردن رسيدانس من ميرها هومز للتطوير العقاري 27
- Project number
- 3486
- Site inspections
- 4
Schedule
Between November 2025 and August 2026 the site added about 4.0 points a month. At that rate it would finish around November 2027, more than three months after its registered date of January 2027.
Site inspections
10 August 2026
40%+20 pts
30 April 2026
20%+14 pts
26 November 2025
6.4%+4.6 pts
31 January 2025
1.9%
Context
International City Phase 3 has 20 projects under construction, 28% built on average.
Own a unit in 27 East End Garden Residences By Mirha Homes Real Estate Development?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 27 East End Garden Residences By Mirha Homes Real Estate Development handover date?
- The registered completion date is January 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on 27 East End Garden Residences By Mirha Homes Real Estate Development?
- 27 East End Garden Residences By Mirha Homes Real Estate Development was 58% built at the site inspection on 10 August 2026. The site has been inspected 4 times since January 2025. The Land Department took 20 site photos at its inspections.
- Is 27 East End Garden Residences By Mirha Homes Real Estate Development delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
- Who is building 27 East End Garden Residences By Mirha Homes Real Estate Development?
- The registered developer is Mirha Homes Real Estate Development.
- Which bank holds the escrow account for 27 East End Garden Residences By Mirha Homes Real Estate Development?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Maiden ResidenceNearby in International City Phase 3. 73%, Due December 2025, passed.
- Linden ResidencesNearby in International City Phase 3. 27%, Due December 2027.
- Moonsa Residences 2Nearby in International City Phase 3. 1.0%, Due December 2026.
- Mayflower ResidencesNearby in International City Phase 3. 96%, Due March 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.