Sunlight Homes construction progress
The registered completion date for Sunlight Homes in International City Phase 3 is September 2027. At the last site inspection, in June 2026, it was 22% built. The developer is Sunn And Sand Developers.
22%
Built, at the site inspection of 1 June 2026
Running behind its date
- Registered completion date
- September 2027
- Finish at recent pace
- April 2029
- Construction started
- June 2025
- First registered
- August 2025
- Developer
- Sunn And Sand Developers
- Community
- International City Phase 3
- Units
- 30
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- صن لايت هومز
- Project number
- 3827
- Site inspections
- 2
Schedule
Between August 2025 and June 2026 the site added about 2.2 points a month. At that rate it would finish around April 2029, more than three months after its registered date of September 2027.
Site inspections
1 June 2026
22%+22 pts
5 August 2025
0%
Context
International City Phase 3 has 20 projects under construction, 28% built on average.
Own a unit in Sunlight Homes?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sunlight Homes handover date?
- The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sunlight Homes?
- Sunlight Homes was 22% built at the site inspection on 1 June 2026. The site has been inspected 2 times since August 2025. The Land Department took 8 site photos at its inspections.
- Is Sunlight Homes delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Sunlight Homes?
- The registered developer is Sunn And Sand Developers.
- Which bank holds the escrow account for Sunlight Homes?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Maiden ResidenceNearby in International City Phase 3. 73%, Due December 2025, passed.
- Linden ResidencesNearby in International City Phase 3. 27%, Due December 2027.
- Moonsa Residences 2Nearby in International City Phase 3. 1.0%, Due December 2026.
- Mayflower ResidencesNearby in International City Phase 3. 96%, Due March 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.