Sunlight Homes construction progress

Sunlight Homes in International City Phase 3 is 22% built at the Land Department inspection of June 2026. Developer Sunn And Sand Developers. Completion registered for September 2027.

22%

Built, at the Land Department site inspection of 1 June 2026

Running behind its date

Completion date (Land Department)
September 2027
Finish at recent pace
April 2029
Construction started
June 2025
Registered with the Land Department
August 2025
Developer
Sunn And Sand Developers
Units
30
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
صن لايت هومز
Land Department project number
3827
Land Department site inspections
2

Schedule

Between August 2025 and June 2026 the site added about 2.2 points a month. At that rate it would finish around April 2029, more than three months after the September 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 June 2026

22%+22 pts

  • Sunlight Homes construction site, Land Department inspection photo 1, 1 June 2026
  • Sunlight Homes construction site, Land Department inspection photo 2, 1 June 2026
  • Sunlight Homes construction site, Land Department inspection photo 3, 1 June 2026
  • Sunlight Homes construction site, Land Department inspection photo 4, 1 June 2026

5 August 2025

0%

  • Sunlight Homes construction site, Land Department inspection photo 1, 5 August 2025
  • Sunlight Homes construction site, Land Department inspection photo 2, 5 August 2025

All 8 site photos, by inspection date

Context

International City Phase 3 has 21 projects under construction, 30% built on average.

Own a unit in Sunlight Homes?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Sunlight Homes be completed?
The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around April 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Sunlight Homes is built?
22%, measured at the Land Department site inspection on 1 June 2026. The Land Department engineers have inspected the site 2 times since August 2025.
Is Sunlight Homes delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Sunlight Homes?
The registered developer is Sunn And Sand Developers.
Which bank holds the escrow account for Sunlight Homes?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.