Mayflower Residences construction progress
Mayflower Residences in International City Phase 3 was registered to complete in March 2026 and is still under construction. At the last site inspection, in October 2026, it was 96% built. The developer is A J G Warsan Real Estate Development.
96%
Built, at the site inspection of 1 October 2026
8 months past its registered completion date
- Registered completion date
- March 2026
- Finish at recent pace
- November 2026
- Construction started
- March 2024
- First registered
- October 2024
- Developer
- A J G Warsan Real Estate Development
- Community
- International City Phase 3
- Units
- 99
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- مساكن ماي فلاور
- Project number
- 3301
- Site inspections
- 8
Schedule
Mayflower Residences was registered to complete in March 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 3.6 points a month. Kept at that rate, the site would reach 100% around November 2026.
Site inspections
1 October 2026
96%+8.2 pts
16 April 2026
88%+20 pts
16 February 2026
68%+10 pts
6 November 2025
57%+21 pts
18 July 2025
37%+10 pts
18 April 2025
27%+15 pts
29 January 2025
11%+4.2 pts
27 September 2024
7.2%
Context
International City Phase 3 has 20 projects under construction, 28% built on average.
Own a unit in Mayflower Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Mayflower Residences handover date?
- The registered completion date was March 2026, and the register still lists Mayflower Residences as under construction. At the pace of its recent inspections the site would reach 100% around November 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Mayflower Residences?
- Mayflower Residences was 96% built at the site inspection on 1 October 2026. The site has been inspected 8 times since September 2024. The Land Department took 69 site photos at its inspections.
- Is Mayflower Residences delayed?
- Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
- Who is building Mayflower Residences?
- The registered developer is A J G Warsan Real Estate Development.
- Which bank holds the escrow account for Mayflower Residences?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Maiden ResidenceNearby in International City Phase 3. 73%, Due December 2025, passed.
- Linden ResidencesNearby in International City Phase 3. 27%, Due December 2027.
- Moonsa Residences 2Nearby in International City Phase 3. 1.0%, Due December 2026.
- 27 East End Garden Residences By Mirha Homes Real Estate DevelopmentNearby in International City Phase 3. 58%, Due January 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)