Mayflower Residences construction progress

Mayflower Residences in International City Phase 3 was registered to complete in March 2026 and is still under construction. At the last site inspection, in October 2026, it was 96% built. The developer is A J G Warsan Real Estate Development.

96%

Built, at the site inspection of 1 October 2026

8 months past its registered completion date

Registered completion date
March 2026
Finish at recent pace
November 2026
Construction started
March 2024
First registered
October 2024
Developer
A J G Warsan Real Estate Development
Units
99
Escrow bank
Dubai Islamic Bank
Name in Arabic
مساكن ماي فلاور
Project number
3301
Site inspections
8

Schedule

Mayflower Residences was registered to complete in March 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 3.6 points a month. Kept at that rate, the site would reach 100% around November 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 October 2026

96%+8.2 pts

  • Mayflower Residences construction site, inspection photo 1, 1 October 2026
  • Mayflower Residences construction site, inspection photo 2, 1 October 2026
  • Mayflower Residences construction site, inspection photo 3, 1 October 2026
  • Mayflower Residences construction site, inspection photo 4, 1 October 2026

16 April 2026

88%+20 pts

  • Mayflower Residences construction site, inspection photo 1, 16 April 2026
  • Mayflower Residences construction site, inspection photo 2, 16 April 2026
  • Mayflower Residences construction site, inspection photo 3, 16 April 2026
  • Mayflower Residences construction site, inspection photo 4, 16 April 2026

16 February 2026

68%+10 pts

  • Mayflower Residences construction site, inspection photo 1, 16 February 2026
  • Mayflower Residences construction site, inspection photo 2, 16 February 2026
  • Mayflower Residences construction site, inspection photo 3, 16 February 2026
  • Mayflower Residences construction site, inspection photo 4, 16 February 2026

6 November 2025

57%+21 pts

  • Mayflower Residences construction site, inspection photo 1, 6 November 2025
  • Mayflower Residences construction site, inspection photo 2, 6 November 2025
  • Mayflower Residences construction site, inspection photo 3, 6 November 2025
  • Mayflower Residences construction site, inspection photo 4, 6 November 2025

18 July 2025

37%+10 pts

  • Mayflower Residences construction site, inspection photo 1, 18 July 2025
  • Mayflower Residences construction site, inspection photo 2, 18 July 2025
  • Mayflower Residences construction site, inspection photo 3, 18 July 2025
  • Mayflower Residences construction site, inspection photo 4, 18 July 2025

18 April 2025

27%+15 pts

  • Mayflower Residences construction site, inspection photo 1, 18 April 2025
  • Mayflower Residences construction site, inspection photo 2, 18 April 2025
  • Mayflower Residences construction site, inspection photo 3, 18 April 2025
  • Mayflower Residences construction site, inspection photo 4, 18 April 2025

29 January 2025

11%+4.2 pts

  • Mayflower Residences construction site, inspection photo 1, 29 January 2025
  • Mayflower Residences construction site, inspection photo 2, 29 January 2025
  • Mayflower Residences construction site, inspection photo 3, 29 January 2025
  • Mayflower Residences construction site, inspection photo 4, 29 January 2025

27 September 2024

7.2%

  • Mayflower Residences construction site, inspection photo 1, 27 September 2024
  • Mayflower Residences construction site, inspection photo 2, 27 September 2024
  • Mayflower Residences construction site, inspection photo 3, 27 September 2024
  • Mayflower Residences construction site, inspection photo 4, 27 September 2024

All 69 site photos, by inspection date

Context

International City Phase 3 has 20 projects under construction, 28% built on average.

Own a unit in Mayflower Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Mayflower Residences handover date?
The registered completion date was March 2026, and the register still lists Mayflower Residences as under construction. At the pace of its recent inspections the site would reach 100% around November 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Mayflower Residences?
Mayflower Residences was 96% built at the site inspection on 1 October 2026. The site has been inspected 8 times since September 2024. The Land Department took 69 site photos at its inspections.
Is Mayflower Residences delayed?
Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
Who is building Mayflower Residences?
The registered developer is A J G Warsan Real Estate Development.
Which bank holds the escrow account for Mayflower Residences?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.