Mayflower Residences construction progress
Mayflower Residences in International City Phase 3 is 96% built at the Land Department inspection of October 2026. Developer A J G Warsan Real Estate Development. Completion registered for March 2026.
96%
Built, at the Land Department site inspection of 1 October 2026
6 months past its registered completion date
- Completion date (Land Department)
- March 2026
- Finish at recent pace
- November 2026
- Construction started
- March 2024
- Registered with the Land Department
- October 2024
- Developer
- A J G Warsan Real Estate Development
- Community
- International City Phase 3
- Units
- 99
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- مساكن ماي فلاور
- Land Department project number
- 3301
- Land Department site inspections
- 8
Schedule
Mayflower Residences was registered to complete in March 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 3.6 points a month. Kept at that rate, the site would reach 100% around November 2026.
Site inspections
1 October 2026
96%+8.2 pts
16 April 2026
88%+20 pts
16 February 2026
68%+10 pts
6 November 2025
57%+21 pts
18 July 2025
37%+10 pts
18 April 2025
27%+15 pts
29 January 2025
11%+4.2 pts
27 September 2024
7.2%
Context
International City Phase 3 has 21 projects under construction, 30% built on average.
Own a unit in Mayflower Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Mayflower Residences be completed?
- The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Mayflower Residences is built?
- 96%, measured at the Land Department site inspection on 1 October 2026. The Land Department engineers have inspected the site 8 times since September 2024.
- Is Mayflower Residences delayed?
- Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
- Who is building Mayflower Residences?
- The registered developer is A J G Warsan Real Estate Development.
- Which bank holds the escrow account for Mayflower Residences?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Moonsa ResidencesNearby in International City Phase 3. 95%, Due August 2025, passed.
- The Maiden ResidenceNearby in International City Phase 3. 73%.
- Linden ResidencesNearby in International City Phase 3. 27%.
- Equiti TowerNearby in International City Phase 3. 70%, Due August 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)