Zenith Residences construction progress

The registered completion date for Zenith Residences in International City Phase 3 is March 2028. At the last site inspection, in October 2026, it was 24% built. The developer is Art Of Amber Real Estate Development.

24%

Built, at the site inspection of 7 October 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
November 2029
Construction started
March 2025
First registered
July 2025
Developer
Art Of Amber Real Estate Development
Units
267
Escrow bank
Mashreq Bank
Name in Arabic
زينيث ريزيدنسز
Project number
3708
Site inspections
3

Schedule

Between March 2026 and October 2026 the site added about 2.0 points a month. At that rate it would finish around November 2029, more than three months after its registered date of March 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 October 2026

24%+13 pts

  • Zenith Residences construction site, inspection photo 1, 7 October 2026
  • Zenith Residences construction site, inspection photo 2, 7 October 2026
  • Zenith Residences construction site, inspection photo 3, 7 October 2026
  • Zenith Residences construction site, inspection photo 4, 7 October 2026

27 March 2026

11%+8.2 pts

  • Zenith Residences construction site, inspection photo 1, 27 March 2026
  • Zenith Residences construction site, inspection photo 2, 27 March 2026

20 May 2025

3.0%

  • Zenith Residences construction site, inspection photo 1, 20 May 2025
  • Zenith Residences construction site, inspection photo 2, 20 May 2025
  • Zenith Residences construction site, inspection photo 3, 20 May 2025
  • Zenith Residences construction site, inspection photo 4, 20 May 2025

All 14 site photos, by inspection date

Context

International City Phase 3 has 20 projects under construction, 28% built on average.

Own a unit in Zenith Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Zenith Residences handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Zenith Residences?
Zenith Residences was 24% built at the site inspection on 7 October 2026. The site has been inspected 3 times since May 2025. The Land Department took 14 site photos at its inspections.
Is Zenith Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Zenith Residences?
The registered developer is Art Of Amber Real Estate Development.
Which bank holds the escrow account for Zenith Residences?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.