Zenith Residences construction progress

Zenith Residences in International City Phase 3 is 24% built at the Land Department inspection of October 2026. Developer Art Of Amber Real Estate Development. Completion registered for March 2028.

24%

Built, at the Land Department site inspection of 7 October 2026

Running behind its date

Completion date (Land Department)
March 2028
Finish at recent pace
November 2029
Construction started
March 2025
Registered with the Land Department
July 2025
Developer
Art Of Amber Real Estate Development
Units
267
Escrow bank
Mashreq Bank
Name in Arabic
زينيث ريزيدنسز
Land Department project number
3708
Land Department site inspections
3

Schedule

Between March 2026 and October 2026 the site added about 2.0 points a month. At that rate it would finish around November 2029, more than three months after the March 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 October 2026

24%+13 pts

  • Zenith Residences construction site, Land Department inspection photo 1, 7 October 2026
  • Zenith Residences construction site, Land Department inspection photo 2, 7 October 2026
  • Zenith Residences construction site, Land Department inspection photo 3, 7 October 2026
  • Zenith Residences construction site, Land Department inspection photo 4, 7 October 2026

27 March 2026

11%+8.2 pts

  • Zenith Residences construction site, Land Department inspection photo 1, 27 March 2026
  • Zenith Residences construction site, Land Department inspection photo 2, 27 March 2026

20 May 2025

3.0%

  • Zenith Residences construction site, Land Department inspection photo 1, 20 May 2025
  • Zenith Residences construction site, Land Department inspection photo 2, 20 May 2025
  • Zenith Residences construction site, Land Department inspection photo 3, 20 May 2025
  • Zenith Residences construction site, Land Department inspection photo 4, 20 May 2025

All 14 site photos, by inspection date

Context

International City Phase 3 has 21 projects under construction, 30% built on average.

Own a unit in Zenith Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Zenith Residences be completed?
The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around November 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Zenith Residences is built?
24%, measured at the Land Department site inspection on 7 October 2026. The Land Department engineers have inspected the site 3 times since May 2025.
Is Zenith Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Zenith Residences?
The registered developer is Art Of Amber Real Estate Development.
Which bank holds the escrow account for Zenith Residences?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.