Zenith Residences construction progress
The registered completion date for Zenith Residences in International City Phase 3 is March 2028. At the last site inspection, in October 2026, it was 24% built. The developer is Art Of Amber Real Estate Development.
24%
Built, at the site inspection of 7 October 2026
Running behind its date
- Registered completion date
- March 2028
- Finish at recent pace
- November 2029
- Construction started
- March 2025
- First registered
- July 2025
- Developer
- Art Of Amber Real Estate Development
- Community
- International City Phase 3
- Units
- 267
- Escrow bank
- Mashreq Bank
- Name in Arabic
- زينيث ريزيدنسز
- Project number
- 3708
- Site inspections
- 3
Schedule
Between March 2026 and October 2026 the site added about 2.0 points a month. At that rate it would finish around November 2029, more than three months after its registered date of March 2028.
Site inspections
7 October 2026
24%+13 pts
27 March 2026
11%+8.2 pts
20 May 2025
3.0%
Context
International City Phase 3 has 20 projects under construction, 28% built on average.
Own a unit in Zenith Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Zenith Residences handover date?
- The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Zenith Residences?
- Zenith Residences was 24% built at the site inspection on 7 October 2026. The site has been inspected 3 times since May 2025. The Land Department took 14 site photos at its inspections.
- Is Zenith Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building Zenith Residences?
- The registered developer is Art Of Amber Real Estate Development.
- Which bank holds the escrow account for Zenith Residences?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Maiden ResidenceNearby in International City Phase 3. 73%, Due December 2025, passed.
- Linden ResidencesNearby in International City Phase 3. 27%, Due December 2027.
- Moonsa Residences 2Nearby in International City Phase 3. 1.0%, Due December 2026.
- Mayflower ResidencesNearby in International City Phase 3. 96%, Due March 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)