Stellar Axis By Ajmal Estate Developers construction progress

Stellar Axis By Ajmal Estate Developers in International City Phase 3 is 27% built at the Land Department inspection of August 2026. Developer Ajmal Estate Developers. Completion registered for October 2026.

27%

Built, at the Land Department site inspection of 10 August 2026

0 months past its registered completion date

Completion date (Land Department)
October 2026
Finish at recent pace
March 2029
Construction started
July 2025
Registered with the Land Department
October 2025
Developer
Ajmal Estate Developers
Units
122
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ستيلار اكسيس من اجمل للتطوير العقاري
Land Department project number
4063
Land Department site inspections
3

Schedule

Stellar Axis By Ajmal Estate Developers was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 2.3 points a month. Kept at that rate, the site would reach 100% around March 2029.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

10 August 2026

27%+12 pts

  • Stellar Axis By Ajmal Estate Developers construction site, Land Department inspection photo 1, 10 August 2026
  • Stellar Axis By Ajmal Estate Developers construction site, Land Department inspection photo 2, 10 August 2026
  • Stellar Axis By Ajmal Estate Developers construction site, Land Department inspection photo 3, 10 August 2026
  • Stellar Axis By Ajmal Estate Developers construction site, Land Department inspection photo 4, 10 August 2026

8 May 2026

15%+15 pts

  • Stellar Axis By Ajmal Estate Developers construction site, Land Department inspection photo 1, 8 May 2026
  • Stellar Axis By Ajmal Estate Developers construction site, Land Department inspection photo 2, 8 May 2026
  • Stellar Axis By Ajmal Estate Developers construction site, Land Department inspection photo 3, 8 May 2026
  • Stellar Axis By Ajmal Estate Developers construction site, Land Department inspection photo 4, 8 May 2026

28 August 2025

0%

  • Stellar Axis By Ajmal Estate Developers construction site, Land Department inspection photo 1, 28 August 2025
  • Stellar Axis By Ajmal Estate Developers construction site, Land Department inspection photo 2, 28 August 2025

All 13 site photos, by inspection date

Context

International City Phase 3 has 21 projects under construction, 30% built on average.

Own a unit in Stellar Axis By Ajmal Estate Developers?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Stellar Axis By Ajmal Estate Developers be completed?
The completion date registered with the Dubai Land Department is October 2026. At the pace of its recent inspections the site would reach 100% around March 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Stellar Axis By Ajmal Estate Developers is built?
27%, measured at the Land Department site inspection on 10 August 2026. The Land Department engineers have inspected the site 3 times since August 2025.
Is Stellar Axis By Ajmal Estate Developers delayed?
Yes. Its registered completion date of October 2026 has passed and the Land Department still lists it as under construction.
Who is building Stellar Axis By Ajmal Estate Developers?
The registered developer is Ajmal Estate Developers.
Which bank holds the escrow account for Stellar Axis By Ajmal Estate Developers?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.