Stellar Axis By Ajmal Estate Developers construction progress

Stellar Axis By Ajmal Estate Developers in International City Phase 3 was registered to complete in October 2026 and is still under construction. At the last site inspection, in November 2026, it was 39% built. The developer is Ajmal Estate Developers.

39%

Built, at the site inspection of 10 November 2026

2 months past its registered completion date

Registered completion date
October 2026
Finish at recent pace
March 2028
Construction started
July 2025
First registered
October 2025
Developer
Ajmal Estate Developers
Units
122
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ستيلار اكسيس من اجمل للتطوير العقاري
Project number
4063
Site inspections
4

Schedule

Stellar Axis By Ajmal Estate Developers was registered to complete in October 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.9 points a month. Kept at that rate, the site would reach 100% around March 2028.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 November 2026

39%+12 pts

  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 1, 10 November 2026
  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 2, 10 November 2026
  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 3, 10 November 2026
  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 4, 10 November 2026

10 August 2026

27%+12 pts

  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 1, 10 August 2026
  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 2, 10 August 2026
  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 3, 10 August 2026
  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 4, 10 August 2026

8 May 2026

15%+15 pts

  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 1, 8 May 2026
  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 2, 8 May 2026
  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 3, 8 May 2026
  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 4, 8 May 2026

28 August 2025

0%

  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 1, 28 August 2025
  • Stellar Axis By Ajmal Estate Developers construction site, inspection photo 2, 28 August 2025

All 23 site photos, by inspection date

Context

International City Phase 3 has 20 projects under construction, 28% built on average.

Own a unit in Stellar Axis By Ajmal Estate Developers?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Stellar Axis By Ajmal Estate Developers handover date?
The registered completion date was October 2026, and the register still lists Stellar Axis By Ajmal Estate Developers as under construction. At the pace of its recent inspections the site would reach 100% around March 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Stellar Axis By Ajmal Estate Developers?
Stellar Axis By Ajmal Estate Developers was 39% built at the site inspection on 10 November 2026. The site has been inspected 4 times since August 2025. The Land Department took 23 site photos at its inspections.
Is Stellar Axis By Ajmal Estate Developers delayed?
Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
Who is building Stellar Axis By Ajmal Estate Developers?
The registered developer is Ajmal Estate Developers.
Which bank holds the escrow account for Stellar Axis By Ajmal Estate Developers?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.