Chapter 01 By Newbury Developments construction progress

Chapter 01 By Newbury Developments in International City Phase 3 is 2.4% built at the Land Department inspection of June 2026. Developer Newbury Real Estate Development. Completion registered for October 2028.

2.4%

Built, at the Land Department site inspection of 25 June 2026

Running behind its date

Completion date (Land Department)
October 2028
Finish at recent pace
January 2068
Construction started
October 2025
Registered with the Land Department
October 2025
Developer
Newbury Real Estate Development
Units
127
Escrow bank
Al Ahli Bank of Kuwait
Name in Arabic
شابتر 1 باي نيوبري ديفيلوبمنتس
Land Department project number
3787
Land Department site inspections
2

Schedule

Between June 2025 and June 2026 the site added about 0.2 points a month. At that rate it would finish around January 2068, more than three months after the October 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 June 2026

2.4%+2.4 pts

  • Chapter 01 By Newbury Developments construction site, Land Department inspection photo 1, 25 June 2026
  • Chapter 01 By Newbury Developments construction site, Land Department inspection photo 2, 25 June 2026
  • Chapter 01 By Newbury Developments construction site, Land Department inspection photo 3, 25 June 2026
  • Chapter 01 By Newbury Developments construction site, Land Department inspection photo 4, 25 June 2026

23 June 2025

0%

  • Chapter 01 By Newbury Developments construction site, Land Department inspection photo 1, 23 June 2025
  • Chapter 01 By Newbury Developments construction site, Land Department inspection photo 2, 23 June 2025

All 6 site photos, by inspection date

Context

International City Phase 3 has 21 projects under construction, 30% built on average.

Own a unit in Chapter 01 By Newbury Developments?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Chapter 01 By Newbury Developments be completed?
The completion date registered with the Dubai Land Department is October 2028. At the pace of its recent inspections the site would reach 100% around January 2068. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Chapter 01 By Newbury Developments is built?
2.4%, measured at the Land Department site inspection on 25 June 2026. The Land Department engineers have inspected the site 2 times since June 2025.
Is Chapter 01 By Newbury Developments delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
Who is building Chapter 01 By Newbury Developments?
The registered developer is Newbury Real Estate Development.
Which bank holds the escrow account for Chapter 01 By Newbury Developments?
Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.