Ventana Residences construction progress
The registered completion date for Ventana Residences in International City Phase 3 is February 2028. At the last site inspection, in October 2026, it was 6.7% built. The developer is Zedor Real Estate Development.
6.7%
Built, at the site inspection of 8 October 2026
Running behind its date
- Registered completion date
- February 2028
- Finish at recent pace
- April 2034
- Construction started
- December 2025
- First registered
- July 2026
- Developer
- Zedor Real Estate Development
- Community
- International City Phase 3
- Units
- 127
- Escrow bank
- United Bank Limited
- Name in Arabic
- فينتانا ريزيدنسز
- Project number
- 3861
- Site inspections
- 3
Schedule
Between June 2026 and October 2026 the site added about 1.0 points a month. At that rate it would finish around April 2034, more than three months after its registered date of February 2028.
Site inspections
8 October 2026
6.7%+4.4 pts
1 June 2026
2.3%+2.3 pts
14 July 2025
0%
Context
International City Phase 3 has 20 projects under construction, 28% built on average.
Own a unit in Ventana Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Ventana Residences handover date?
- The registered completion date is February 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Ventana Residences?
- Ventana Residences was 6.7% built at the site inspection on 8 October 2026. The site has been inspected 3 times since July 2025. The Land Department took 13 site photos at its inspections.
- Is Ventana Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
- Who is building Ventana Residences?
- The registered developer is Zedor Real Estate Development.
- Which bank holds the escrow account for Ventana Residences?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Maiden ResidenceNearby in International City Phase 3. 73%, Due December 2025, passed.
- Linden ResidencesNearby in International City Phase 3. 27%, Due December 2027.
- Moonsa Residences 2Nearby in International City Phase 3. 1.0%, Due December 2026.
- Mayflower ResidencesNearby in International City Phase 3. 96%, Due March 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.