Ventana Residences construction progress

The registered completion date for Ventana Residences in International City Phase 3 is February 2028. At the last site inspection, in October 2026, it was 6.7% built. The developer is Zedor Real Estate Development.

6.7%

Built, at the site inspection of 8 October 2026

Running behind its date

Registered completion date
February 2028
Finish at recent pace
April 2034
Construction started
December 2025
First registered
July 2026
Developer
Zedor Real Estate Development
Units
127
Escrow bank
United Bank Limited
Name in Arabic
فينتانا ريزيدنسز
Project number
3861
Site inspections
3

Schedule

Between June 2026 and October 2026 the site added about 1.0 points a month. At that rate it would finish around April 2034, more than three months after its registered date of February 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 October 2026

6.7%+4.4 pts

  • Ventana Residences construction site, inspection photo 1, 8 October 2026
  • Ventana Residences construction site, inspection photo 2, 8 October 2026
  • Ventana Residences construction site, inspection photo 3, 8 October 2026
  • Ventana Residences construction site, inspection photo 4, 8 October 2026

1 June 2026

2.3%+2.3 pts

  • Ventana Residences construction site, inspection photo 1, 1 June 2026
  • Ventana Residences construction site, inspection photo 2, 1 June 2026
  • Ventana Residences construction site, inspection photo 3, 1 June 2026
  • Ventana Residences construction site, inspection photo 4, 1 June 2026

14 July 2025

0%

  • Ventana Residences construction site, inspection photo 1, 14 July 2025
  • Ventana Residences construction site, inspection photo 2, 14 July 2025

All 13 site photos, by inspection date

Context

International City Phase 3 has 20 projects under construction, 28% built on average.

Own a unit in Ventana Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ventana Residences handover date?
The registered completion date is February 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ventana Residences?
Ventana Residences was 6.7% built at the site inspection on 8 October 2026. The site has been inspected 3 times since July 2025. The Land Department took 13 site photos at its inspections.
Is Ventana Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
Who is building Ventana Residences?
The registered developer is Zedor Real Estate Development.
Which bank holds the escrow account for Ventana Residences?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.