Emaar Dubai South Dwc projects under construction
Emaar Dubai South Dwc has 22 projects under construction in Dubai, according to the Dubai Land Department. On average they are 18% built. The next one due is Greenway 2, in May 2028.
- Fairway Villas 3Dubai World Central49%No date set
- Greenville 2Dubai World Central47%Due March 2029
- GreenvilleDubai World Central46%Due March 2029
- GreenspointDubai World Central43%Due March 2029
- Greenspoint 2Dubai World Central40%Due March 2029
- GreenwayDubai World Central39%No date set
- GreenridgeDubai World Central36%Due December 2028
- Greenway 2Dubai World Central34%Due May 2028
- Golf LaneDubai World Central30%No date set
- Golf PointDubai World Central4.8%Due October 2028
- Golf MeadowDubai World Central4.5%Due July 2029
- Golf VergeDubai World Central4.2%Due May 2029
- Golf Hills 2Dubai World Central4.2%Due September 2029
- Golf HillsDubai World Central3.7%Due September 2029
- Golf AcresDubai World Central3.5%Due December 2028
- Golf DaleDubai World Central0.3%Due December 2028
- Golf EdgeDubai World Central0%No date set
- Golf Fields0%Due February 2030
- Golf Trails0%No date set
- Golf Vale0%Due March 2030
- Grove Ridge0%Due September 2029
- Vista Ridge0%Due September 2029
Reading these figures
Each percentage is the share of construction Land Department engineers recorded at their latest site visit. The completion date is the one the developer registered with the Land Department, and developers can apply to move it. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.