Golf Fields construction progress
Golf Fields is 0% built at the Land Department inspection of August 2026. Developer Emaar Dubai South Dwc. Completion registered for February 2030.
0%
Built, at the Land Department site inspection of 6 August 2026
Running behind its date
- Completion date (Land Department)
- February 2030
- Construction started
- April 2026
- Registered with the Land Department
- February 2026
- Developer
- Emaar Dubai South Dwc
- Units
- 181
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- جولف فيلدز
- Land Department project number
- 4415
- Land Department site inspections
- 2
Schedule
Site inspections
6 August 2026
0%
24 February 2026
0%
Context
Emaar Dubai South Dwc has 22 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Golf Fields?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Golf Fields be completed?
- The completion date registered with the Dubai Land Department is February 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Golf Fields is built?
- 0%, measured at the Land Department site inspection on 6 August 2026. The Land Department engineers have inspected the site 2 times since February 2026.
- Is Golf Fields delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2030.
- Who is building Golf Fields?
- The registered developer is Emaar Dubai South Dwc. It has 21 other projects under construction in Dubai.
- Which bank holds the escrow account for Golf Fields?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Fairway Villas 3Also by Emaar Dubai South Dwc. 49%.
- GreenwayAlso by Emaar Dubai South Dwc. 39%.
- Golf LaneAlso by Emaar Dubai South Dwc. 30%.
- Greenway 2Also by Emaar Dubai South Dwc. 34%, Due May 2028.
- Deyaar ParkNearby in . 0%, Due December 2012, passed.
- Varazze TowerNearby in . 92%, Due February 2024, passed.
- Niki Lauda TowerNearby in . 0.4%.
- Champions Tower2Nearby in . 78%, Due October 2017, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.