Dubai Hills Estate projects under construction
Dubai Hills Estate has 18 projects under construction in Dubai. On average they are 42% built. The next one due is Park Gate 2, in February 2027.
- Greenside ResidenceDubai Hills Estate97%No date set
- Park GateDubai Hills90%No date set
- Club PlaceDubai Hills Estate69%Due December 2028
- Parkside HillsDubai Hills Estate68%Due June 2028
- Golf HillsideDubai Hills Estate66%Due December 2028
- Park LaneDubai Hills Estate55%Due October 2028
- Park Gate 2Dubai Hills55%Due February 2027
- Palace Residences Dubai Hills EstateDubai Hills Estate51%Due April 2028
- ParklandDubai Hills Estate50%Due November 2028
- Vida Residences Club PointDubai Hills Estate44%Due February 2029
- Address Residences L Dubai Hills EstateDubai Hills Estate26%Due February 2029
- HillsedgeDubai Hills Estate26%Due January 2029
- Palace Residences Hillside ADubai Hills Estate16%Due June 2029
- ParkwoodDubai Hills Estate15%Due January 2029
- Vida Residences HillsideDubai Hills Estate10%Due May 2029
- RosehillDubai Hills Estate7.8%Due June 2029
- Greencrest1.2%Due June 2029
- Palace Residences Hillside B0%Due October 2029
Questions
How many projects is Dubai Hills Estate building in Dubai?
18 projects are under construction, 42% built on average at the latest site inspections.
Which Dubai Hills Estate projects finish next?
By registered completion date: Park Gate 2 (February 2027, 55% built), Palace Residences Dubai Hills Estate (April 2028, 51% built) and Parkside Hills (June 2028, 68% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
Are any Dubai Hills Estate projects delayed?
No. Every one of its projects with a registered completion date is still inside it.
Where is Dubai Hills Estate building?
Its projects are in Dubai Hills Estate (14) and Dubai Hills (2).
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.