Park Gate 2 construction progress

Park Gate 2 in Dubai Hills is 55% built at the Land Department inspection of June 2026. Developer Dubai Hills Estate. Completion registered for February 2027.

55%

Built, at the Land Department site inspection of 8 June 2026

On pace for its date

Completion date (Land Department)
February 2027
Finish at recent pace
February 2027
Construction started
June 2025
Registered with the Land Department
April 2025
Community
Dubai Hills
Units
17
Escrow bank
Emirates NBD
Name in Arabic
بارك جيت 2
Land Department project number
3641
Land Department site inspections
5

Schedule

Since July 2025 Park Gate 2 has added about 5.2 points a month. That puts 100% around February 2027, within three months of its registered completion date of February 2027.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

8 June 2026

55%+7.5 pts

  • Park Gate 2 construction site, Land Department inspection photo 1, 8 June 2026
  • Park Gate 2 construction site, Land Department inspection photo 2, 8 June 2026
  • Park Gate 2 construction site, Land Department inspection photo 3, 8 June 2026
  • Park Gate 2 construction site, Land Department inspection photo 4, 8 June 2026

19 February 2026

48%+31 pts

  • Park Gate 2 construction site, Land Department inspection photo 1, 19 February 2026
  • Park Gate 2 construction site, Land Department inspection photo 2, 19 February 2026
  • Park Gate 2 construction site, Land Department inspection photo 3, 19 February 2026
  • Park Gate 2 construction site, Land Department inspection photo 4, 19 February 2026

5 November 2025

17%+15 pts

  • Park Gate 2 construction site, Land Department inspection photo 1, 5 November 2025
  • Park Gate 2 construction site, Land Department inspection photo 2, 5 November 2025
  • Park Gate 2 construction site, Land Department inspection photo 3, 5 November 2025
  • Park Gate 2 construction site, Land Department inspection photo 4, 5 November 2025

30 July 2025

2.2%+2.2 pts

  • Park Gate 2 construction site, Land Department inspection photo 1, 30 July 2025
  • Park Gate 2 construction site, Land Department inspection photo 2, 30 July 2025
  • Park Gate 2 construction site, Land Department inspection photo 3, 30 July 2025
  • Park Gate 2 construction site, Land Department inspection photo 4, 30 July 2025

2 April 2025

0%

  • Park Gate 2 construction site, Land Department inspection photo 1, 2 April 2025
  • Park Gate 2 construction site, Land Department inspection photo 2, 2 April 2025

All 40 site photos, by inspection date

Context

Dubai Hills has 2 projects under construction, 73% built on average.

Dubai Hills Estate has 19 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Park Gate 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Park Gate 2 be completed?
The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around February 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Park Gate 2 is built?
55%, measured at the Land Department site inspection on 8 June 2026. The Land Department engineers have inspected the site 5 times since April 2025.
Is Park Gate 2 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of February 2027.
Who is building Park Gate 2?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Park Gate 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.