Park Gate 2 construction progress
The registered completion date for Park Gate 2 in Dubai Hills is February 2027. At the last site inspection, in June 2026, it was 55% built. The developer is Dubai Hills Estate.
55%
Built, at the site inspection of 8 June 2026
On pace for its date
- Registered completion date
- February 2027
- Finish at recent pace
- February 2027
- Construction started
- June 2025
- First registered
- April 2025
- Developer
- Dubai Hills Estate
- Community
- Dubai Hills
- Units
- 17
- Escrow bank
- Emirates NBD
- Name in Arabic
- بارك جيت 2
- Project number
- 3641
- Site inspections
- 5
Schedule
Since July 2025 Park Gate 2 has added about 5.2 points a month. That puts 100% around February 2027, within three months of its registered completion date of February 2027.
Site inspections
8 June 2026
55%+7.5 pts
19 February 2026
48%+31 pts
5 November 2025
17%+15 pts
30 July 2025
2.2%+2.2 pts
2 April 2025
0%
Context
Dubai Hills has 2 projects under construction, 73% built on average.
Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Park Gate 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Park Gate 2 handover date?
- The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Park Gate 2?
- Park Gate 2 was 55% built at the site inspection on 8 June 2026. The site has been inspected 5 times since April 2025. The Land Department took 40 site photos at its inspections.
- Is Park Gate 2 delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of February 2027.
- Who is building Park Gate 2?
- The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for Park Gate 2?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Greenside ResidenceAlso by Dubai Hills Estate. 97%.
- Parkside HillsAlso by Dubai Hills Estate. 68%, Due June 2028.
- Park LaneAlso by Dubai Hills Estate. 55%, Due October 2028.
- Park GateAlso by Dubai Hills Estate. 90%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)