Park Gate construction progress
No completion date is registered for Park Gate in Dubai Hills yet. At the last site inspection, in August 2026, it was 90% built. The developer is Dubai Hills Estate.
90%
Built, at the site inspection of 11 August 2026
- Finish at recent pace
- October 2026
- Construction started
- May 2024
- First registered
- November 2023
- Developer
- Dubai Hills Estate
- Community
- Dubai Hills
- Units
- 47
- Escrow bank
- Emirates NBD
- Name in Arabic
- بارك جيت
- Project number
- 2846
- Site inspections
- 9
Schedule
Since September 2025 Park Gate has added about 3.7 points a month. At that rate the site reaches 100% around October 2026. No completion date is on record to compare it with.
Site inspections
11 August 2026
90%+7.2 pts
3 June 2026
83%+12 pts
12 February 2026
72%+5.7 pts
5 January 2026
66%+16 pts
19 September 2025
50%+29 pts
18 April 2025
21%+14 pts
18 November 2024
7.2%+6.1 pts
6 June 2024
1.1%+1.1 pts
14 November 2023
0%
Context
Dubai Hills has 2 projects under construction, 73% built on average.
Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Park Gate?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Park Gate handover date?
- No completion date is on record for Park Gate yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Park Gate?
- Park Gate was 90% built at the site inspection on 11 August 2026. The site has been inspected 9 times since November 2023. The Land Department took 78 site photos at its inspections.
- Who is building Park Gate?
- The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for Park Gate?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Greenside ResidenceAlso by Dubai Hills Estate. 97%.
- Parkside HillsAlso by Dubai Hills Estate. 68%, Due June 2028.
- Park LaneAlso by Dubai Hills Estate. 55%, Due October 2028.
- Palace Residences Dubai Hills EstateAlso by Dubai Hills Estate. 51%, Due April 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.