Address Residences L Dubai Hills Estate construction progress

The registered completion date for Address Residences L Dubai Hills Estate in Dubai Hills Estate is February 2029. At the last site inspection, in June 2026, it was 26% built. The developer is Dubai Hills Estate.

26%

Built, at the site inspection of 10 June 2026

On pace for its date

Registered completion date
February 2029
Finish at recent pace
February 2029
Construction started
December 2024
First registered
August 2024
Units
582
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
دبي هيلز استيت L العنوان رزيدنسز
Project number
3228
Site inspections
5

Schedule

Since September 2025 Address Residences L Dubai Hills Estate has added about 2.3 points a month. That puts 100% around February 2029, within three months of its registered completion date of February 2029.

0%25%50%75%100%20252026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 June 2026

26%+16 pts

  • Address Residences L Dubai Hills Estate construction site, inspection photo 1, 10 June 2026
  • Address Residences L Dubai Hills Estate construction site, inspection photo 2, 10 June 2026
  • Address Residences L Dubai Hills Estate construction site, inspection photo 3, 10 June 2026
  • Address Residences L Dubai Hills Estate construction site, inspection photo 4, 10 June 2026

15 February 2026

10%+4.3 pts

  • Address Residences L Dubai Hills Estate construction site, inspection photo 1, 15 February 2026
  • Address Residences L Dubai Hills Estate construction site, inspection photo 2, 15 February 2026
  • Address Residences L Dubai Hills Estate construction site, inspection photo 3, 15 February 2026
  • Address Residences L Dubai Hills Estate construction site, inspection photo 4, 15 February 2026

8 September 2025

5.8%+4.3 pts

  • Address Residences L Dubai Hills Estate construction site, inspection photo 1, 8 September 2025
  • Address Residences L Dubai Hills Estate construction site, inspection photo 2, 8 September 2025
  • Address Residences L Dubai Hills Estate construction site, inspection photo 3, 8 September 2025
  • Address Residences L Dubai Hills Estate construction site, inspection photo 4, 8 September 2025

7 May 2025

1.4%+1.4 pts

  • Address Residences L Dubai Hills Estate construction site, inspection photo 1, 7 May 2025
  • Address Residences L Dubai Hills Estate construction site, inspection photo 2, 7 May 2025
  • Address Residences L Dubai Hills Estate construction site, inspection photo 3, 7 May 2025
  • Address Residences L Dubai Hills Estate construction site, inspection photo 4, 7 May 2025

12 August 2024

0%

  • Address Residences L Dubai Hills Estate construction site, inspection photo 1, 12 August 2024
  • Address Residences L Dubai Hills Estate construction site, inspection photo 2, 12 August 2024
  • Address Residences L Dubai Hills Estate construction site, inspection photo 3, 12 August 2024

All 25 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Address Residences L Dubai Hills Estate?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Address Residences L Dubai Hills Estate handover date?
The registered completion date is February 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Address Residences L Dubai Hills Estate?
Address Residences L Dubai Hills Estate was 26% built at the site inspection on 10 June 2026. The site has been inspected 5 times since August 2024. The Land Department took 25 site photos at its inspections.
Is Address Residences L Dubai Hills Estate delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of February 2029.
Who is building Address Residences L Dubai Hills Estate?
The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Address Residences L Dubai Hills Estate?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.