Golf Hillside construction progress
The registered completion date for Golf Hillside in Dubai Hills Estate is December 2028. At the last site inspection, in August 2026, it was 66% built. The developer is Dubai Hills Estate.
66%
Built, at the site inspection of 11 August 2026
On pace for its date
- Registered completion date
- December 2028
- Finish at recent pace
- May 2027
- Construction started
- October 2024
- First registered
- September 2024
- Developer
- Dubai Hills Estate
- Community
- Dubai Hills Estate
- Units
- 185
- Escrow bank
- Mashreq Bank
- Name in Arabic
- جولف هيلسايد
- Project number
- 3237
- Site inspections
- 7
Schedule
Since September 2025 Golf Hillside has added about 3.9 points a month. That puts 100% around May 2027, within three months of its registered completion date of December 2028.
Site inspections
11 August 2026
66%+11 pts
21 April 2026
55%+18 pts
5 January 2026
37%+13 pts
17 September 2025
24%+9.5 pts
18 June 2025
14%+7.3 pts
12 March 2025
7.1%+7.1 pts
15 August 2024
0%
Context
Dubai Hills Estate has 19 projects under construction, 44% built on average.
Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Golf Hillside?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Golf Hillside handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Golf Hillside?
- Golf Hillside was 66% built at the site inspection on 11 August 2026. The site has been inspected 7 times since August 2024. The Land Department took 39 site photos at its inspections.
- Is Golf Hillside delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2028.
- Who is building Golf Hillside?
- The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for Golf Hillside?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Greenside ResidenceAlso by Dubai Hills Estate. 97%.
- Parkside HillsAlso by Dubai Hills Estate. 68%, Due June 2028.
- Park LaneAlso by Dubai Hills Estate. 55%, Due October 2028.
- Park GateAlso by Dubai Hills Estate. 90%.
- Ellington House IVNearby in Dubai Hills Estate. 70%.
- Mallside ResidenceNearby in Dubai Hills Estate. 83%, Due November 2026.
- Soho The BerkeleyNearby in Dubai Hills Estate. 46%, Due October 2026, passed.
- City View Dubai Hills ResidencesNearby in Dubai Hills Estate. 39%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.