Golf Hillside construction progress

The registered completion date for Golf Hillside in Dubai Hills Estate is December 2028. At the last site inspection, in August 2026, it was 66% built. The developer is Dubai Hills Estate.

66%

Built, at the site inspection of 11 August 2026

On pace for its date

Registered completion date
December 2028
Finish at recent pace
May 2027
Construction started
October 2024
First registered
September 2024
Units
185
Escrow bank
Mashreq Bank
Name in Arabic
جولف هيلسايد
Project number
3237
Site inspections
7

Schedule

Since September 2025 Golf Hillside has added about 3.9 points a month. That puts 100% around May 2027, within three months of its registered completion date of December 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 August 2026

66%+11 pts

  • Golf Hillside construction site, inspection photo 1, 11 August 2026
  • Golf Hillside construction site, inspection photo 2, 11 August 2026
  • Golf Hillside construction site, inspection photo 3, 11 August 2026
  • Golf Hillside construction site, inspection photo 4, 11 August 2026

21 April 2026

55%+18 pts

  • Golf Hillside construction site, inspection photo 1, 21 April 2026
  • Golf Hillside construction site, inspection photo 2, 21 April 2026
  • Golf Hillside construction site, inspection photo 3, 21 April 2026
  • Golf Hillside construction site, inspection photo 4, 21 April 2026

5 January 2026

37%+13 pts

  • Golf Hillside construction site, inspection photo 1, 5 January 2026
  • Golf Hillside construction site, inspection photo 2, 5 January 2026
  • Golf Hillside construction site, inspection photo 3, 5 January 2026
  • Golf Hillside construction site, inspection photo 4, 5 January 2026

17 September 2025

24%+9.5 pts

  • Golf Hillside construction site, inspection photo 1, 17 September 2025
  • Golf Hillside construction site, inspection photo 2, 17 September 2025
  • Golf Hillside construction site, inspection photo 3, 17 September 2025
  • Golf Hillside construction site, inspection photo 4, 17 September 2025

18 June 2025

14%+7.3 pts

  • Golf Hillside construction site, inspection photo 1, 18 June 2025
  • Golf Hillside construction site, inspection photo 2, 18 June 2025
  • Golf Hillside construction site, inspection photo 3, 18 June 2025
  • Golf Hillside construction site, inspection photo 4, 18 June 2025

12 March 2025

7.1%+7.1 pts

  • Golf Hillside construction site, inspection photo 1, 12 March 2025
  • Golf Hillside construction site, inspection photo 2, 12 March 2025
  • Golf Hillside construction site, inspection photo 3, 12 March 2025
  • Golf Hillside construction site, inspection photo 4, 12 March 2025

15 August 2024

0%

  • Golf Hillside construction site, inspection photo 1, 15 August 2024
  • Golf Hillside construction site, inspection photo 2, 15 August 2024

All 39 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Golf Hillside?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Golf Hillside handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Golf Hillside?
Golf Hillside was 66% built at the site inspection on 11 August 2026. The site has been inspected 7 times since August 2024. The Land Department took 39 site photos at its inspections.
Is Golf Hillside delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2028.
Who is building Golf Hillside?
The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Golf Hillside?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.