Vida Residences Hillside construction progress

Vida Residences Hillside in Dubai Hills Estate is 10% built at the Land Department inspection of May 2026. Developer Dubai Hills Estate. Completion registered for May 2029.

10%

Built, at the Land Department site inspection of 4 May 2026

Running behind its date

Completion date (Land Department)
May 2029
Finish at recent pace
July 2032
Construction started
June 2025
Registered with the Land Department
February 2025
Units
500
Escrow bank
Emirates Islamic Bank
Name in Arabic
فيدا ريزيدنسزهيلسايد
Land Department project number
3534
Land Department site inspections
4

Schedule

Between September 2025 and May 2026 the site added about 1.2 points a month. At that rate it would finish around July 2032, more than three months after the May 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

4 May 2026

10%+5.0 pts

  • Vida Residences Hillside construction site, Land Department inspection photo 1, 4 May 2026
  • Vida Residences Hillside construction site, Land Department inspection photo 2, 4 May 2026
  • Vida Residences Hillside construction site, Land Department inspection photo 3, 4 May 2026

14 January 2026

5.0%+4.4 pts

  • Vida Residences Hillside construction site, Land Department inspection photo 1, 14 January 2026
  • Vida Residences Hillside construction site, Land Department inspection photo 2, 14 January 2026
  • Vida Residences Hillside construction site, Land Department inspection photo 3, 14 January 2026
  • Vida Residences Hillside construction site, Land Department inspection photo 4, 14 January 2026

10 September 2025

0.6%+0.6 pts

  • Vida Residences Hillside construction site, Land Department inspection photo 1, 10 September 2025
  • Vida Residences Hillside construction site, Land Department inspection photo 2, 10 September 2025
  • Vida Residences Hillside construction site, Land Department inspection photo 3, 10 September 2025
  • Vida Residences Hillside construction site, Land Department inspection photo 4, 10 September 2025

4 February 2025

0%

  • Vida Residences Hillside construction site, Land Department inspection photo 1, 4 February 2025
  • Vida Residences Hillside construction site, Land Department inspection photo 2, 4 February 2025

All 13 site photos, by inspection date

Context

Dubai Hills Estate has 20 projects under construction, 45% built on average.

Dubai Hills Estate has 19 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Vida Residences Hillside?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Vida Residences Hillside be completed?
The completion date registered with the Dubai Land Department is May 2029. At the pace of its recent inspections the site would reach 100% around July 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Vida Residences Hillside is built?
10%, measured at the Land Department site inspection on 4 May 2026. The Land Department engineers have inspected the site 4 times since February 2025.
Is Vida Residences Hillside delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2029.
Who is building Vida Residences Hillside?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Vida Residences Hillside?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.