Palace Residences Dubai Hills Estate construction progress
The registered completion date for Palace Residences Dubai Hills Estate in Dubai Hills Estate is April 2028. At the last site inspection, in June 2026, it was 51% built. The developer is Dubai Hills Estate.
51%
Built, at the site inspection of 16 June 2026
On pace for its date
- Registered completion date
- April 2028
- Finish at recent pace
- June 2027
- Construction started
- March 2024
- First registered
- December 2023
- Developer
- Dubai Hills Estate
- Community
- Dubai Hills Estate
- Units
- 962
- Escrow bank
- Mashreq Bank
- Name in Arabic
- بالاس رزيدنسز دبي هيلز استيت
- Project number
- 2884
- Site inspections
- 7
Schedule
Since October 2025 Palace Residences Dubai Hills Estate has added about 4.0 points a month. That puts 100% around June 2027, within three months of its registered completion date of April 2028.
Site inspections
16 June 2026
51%+14 pts
12 February 2026
37%+20 pts
1 October 2025
17%+7.7 pts
12 May 2025
9.2%+3.9 pts
22 January 2025
5.3%+4.1 pts
1 October 2024
1.2%+1.2 pts
18 December 2023
0%
Context
Dubai Hills Estate has 19 projects under construction, 44% built on average.
Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Palace Residences Dubai Hills Estate?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Palace Residences Dubai Hills Estate handover date?
- The registered completion date is April 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Palace Residences Dubai Hills Estate?
- Palace Residences Dubai Hills Estate was 51% built at the site inspection on 16 June 2026. The site has been inspected 7 times since December 2023. The Land Department took 45 site photos at its inspections.
- Is Palace Residences Dubai Hills Estate delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of April 2028.
- Who is building Palace Residences Dubai Hills Estate?
- The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for Palace Residences Dubai Hills Estate?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Greenside ResidenceAlso by Dubai Hills Estate. 97%.
- Parkside HillsAlso by Dubai Hills Estate. 68%, Due June 2028.
- Park LaneAlso by Dubai Hills Estate. 55%, Due October 2028.
- Park GateAlso by Dubai Hills Estate. 90%.
- Ellington House IVNearby in Dubai Hills Estate. 70%.
- Mallside ResidenceNearby in Dubai Hills Estate. 83%, Due November 2026.
- Soho The BerkeleyNearby in Dubai Hills Estate. 46%, Due October 2026, passed.
- City View Dubai Hills ResidencesNearby in Dubai Hills Estate. 39%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)