Hillsedge construction progress

Hillsedge in Dubai Hills Estate is 26% built at the Land Department inspection of June 2026. Developer Dubai Hills Estate. Completion registered for January 2029.

26%

Built, at the Land Department site inspection of 6 June 2026

Running behind its date

Completion date (Land Department)
January 2029
Finish at recent pace
June 2029
Construction started
May 2025
Registered with the Land Department
November 2024
Units
406
Escrow bank
First Abu Dhabi Bank
Name in Arabic
هيلسيدج
Land Department project number
3411
Land Department site inspections
5

Schedule

Between July 2025 and June 2026 the site added about 2.1 points a month. At that rate it would finish around June 2029, more than three months after the January 2029 date registered with the Land Department.

0%25%50%75%100%20252026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 June 2026

26%+11 pts

  • Hillsedge construction site, Land Department inspection photo 1, 6 June 2026
  • Hillsedge construction site, Land Department inspection photo 2, 6 June 2026
  • Hillsedge construction site, Land Department inspection photo 3, 6 June 2026
  • Hillsedge construction site, Land Department inspection photo 4, 6 June 2026

17 March 2026

15%+9.8 pts

  • Hillsedge construction site, Land Department inspection photo 1, 17 March 2026
  • Hillsedge construction site, Land Department inspection photo 2, 17 March 2026
  • Hillsedge construction site, Land Department inspection photo 3, 17 March 2026
  • Hillsedge construction site, Land Department inspection photo 4, 17 March 2026

5 November 2025

5.0%+2.5 pts

  • Hillsedge construction site, Land Department inspection photo 1, 5 November 2025
  • Hillsedge construction site, Land Department inspection photo 2, 5 November 2025
  • Hillsedge construction site, Land Department inspection photo 3, 5 November 2025

1 July 2025

2.5%+2.5 pts

  • Hillsedge construction site, Land Department inspection photo 1, 1 July 2025
  • Hillsedge construction site, Land Department inspection photo 2, 1 July 2025
  • Hillsedge construction site, Land Department inspection photo 3, 1 July 2025
  • Hillsedge construction site, Land Department inspection photo 4, 1 July 2025

19 November 2024

0%

  • Hillsedge construction site, Land Department inspection photo 1, 19 November 2024
  • Hillsedge construction site, Land Department inspection photo 2, 19 November 2024

All 26 site photos, by inspection date

Context

Dubai Hills Estate has 20 projects under construction, 45% built on average.

Dubai Hills Estate has 19 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Hillsedge?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Hillsedge be completed?
The completion date registered with the Dubai Land Department is January 2029. At the pace of its recent inspections the site would reach 100% around June 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Hillsedge is built?
26%, measured at the Land Department site inspection on 6 June 2026. The Land Department engineers have inspected the site 5 times since November 2024.
Is Hillsedge delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2029.
Who is building Hillsedge?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Hillsedge?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.