Vida Residences Club Point construction progress
The registered completion date for Vida Residences Club Point in Dubai Hills Estate is February 2029. At the last site inspection, in August 2026, it was 44% built. The developer is Dubai Hills Estate.
44%
Built, at the site inspection of 3 August 2026
On pace for its date
- Registered completion date
- February 2029
- Finish at recent pace
- April 2028
- Construction started
- November 2024
- First registered
- September 2024
- Developer
- Dubai Hills Estate
- Community
- Dubai Hills Estate
- Units
- 672
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- فيدا رزيدنسز كلوب بوينت
- Project number
- 3309
- Site inspections
- 6
Schedule
Since September 2025 Vida Residences Club Point has added about 2.8 points a month. That puts 100% around April 2028, within three months of its registered completion date of February 2029.
Site inspections
3 August 2026
44%+7.0 pts
22 April 2026
37%+14 pts
5 January 2026
23%+9.3 pts
9 September 2025
14%+7.2 pts
8 May 2025
6.3%+6.3 pts
23 September 2024
0%
Context
Dubai Hills Estate has 19 projects under construction, 44% built on average.
Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Vida Residences Club Point?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Vida Residences Club Point handover date?
- The registered completion date is February 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Vida Residences Club Point?
- Vida Residences Club Point was 44% built at the site inspection on 3 August 2026. The site has been inspected 6 times since September 2024. The Land Department took 42 site photos at its inspections.
- Is Vida Residences Club Point delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of February 2029.
- Who is building Vida Residences Club Point?
- The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for Vida Residences Club Point?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Greenside ResidenceAlso by Dubai Hills Estate. 97%.
- Parkside HillsAlso by Dubai Hills Estate. 68%, Due June 2028.
- Park LaneAlso by Dubai Hills Estate. 55%, Due October 2028.
- Park GateAlso by Dubai Hills Estate. 90%.
- Ellington House IVNearby in Dubai Hills Estate. 70%.
- Mallside ResidenceNearby in Dubai Hills Estate. 83%, Due November 2026.
- Soho The BerkeleyNearby in Dubai Hills Estate. 46%, Due October 2026, passed.
- City View Dubai Hills ResidencesNearby in Dubai Hills Estate. 39%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.












.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)