Vida Residences Club Point construction progress

Vida Residences Club Point in Dubai Hills Estate is 44% built at the Land Department inspection of August 2026. Developer Dubai Hills Estate. Completion registered for February 2029.

44%

Built, at the Land Department site inspection of 3 August 2026

On pace for its date

Completion date (Land Department)
February 2029
Finish at recent pace
April 2028
Construction started
November 2024
Registered with the Land Department
September 2024
Units
672
Escrow bank
First Abu Dhabi Bank
Name in Arabic
فيدا رزيدنسز كلوب بوينت
Land Department project number
3309
Land Department site inspections
6

Schedule

Since September 2025 Vida Residences Club Point has added about 2.8 points a month. That puts 100% around April 2028, within three months of its registered completion date of February 2029.

0%25%50%75%100%20252026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 August 2026

44%+7.0 pts

  • Vida Residences Club Point construction site, Land Department inspection photo 1, 3 August 2026
  • Vida Residences Club Point construction site, Land Department inspection photo 2, 3 August 2026
  • Vida Residences Club Point construction site, Land Department inspection photo 3, 3 August 2026
  • Vida Residences Club Point construction site, Land Department inspection photo 4, 3 August 2026

22 April 2026

37%+14 pts

  • Vida Residences Club Point construction site, Land Department inspection photo 1, 22 April 2026
  • Vida Residences Club Point construction site, Land Department inspection photo 2, 22 April 2026
  • Vida Residences Club Point construction site, Land Department inspection photo 3, 22 April 2026
  • Vida Residences Club Point construction site, Land Department inspection photo 4, 22 April 2026

5 January 2026

23%+9.3 pts

  • Vida Residences Club Point construction site, Land Department inspection photo 1, 5 January 2026
  • Vida Residences Club Point construction site, Land Department inspection photo 2, 5 January 2026
  • Vida Residences Club Point construction site, Land Department inspection photo 3, 5 January 2026
  • Vida Residences Club Point construction site, Land Department inspection photo 4, 5 January 2026

9 September 2025

14%+7.2 pts

  • Vida Residences Club Point construction site, Land Department inspection photo 1, 9 September 2025
  • Vida Residences Club Point construction site, Land Department inspection photo 2, 9 September 2025
  • Vida Residences Club Point construction site, Land Department inspection photo 3, 9 September 2025
  • Vida Residences Club Point construction site, Land Department inspection photo 4, 9 September 2025

8 May 2025

6.3%+6.3 pts

  • Vida Residences Club Point construction site, Land Department inspection photo 1, 8 May 2025
  • Vida Residences Club Point construction site, Land Department inspection photo 2, 8 May 2025
  • Vida Residences Club Point construction site, Land Department inspection photo 3, 8 May 2025
  • Vida Residences Club Point construction site, Land Department inspection photo 4, 8 May 2025

23 September 2024

0%

  • Vida Residences Club Point construction site, Land Department inspection photo 1, 23 September 2024
  • Vida Residences Club Point construction site, Land Department inspection photo 2, 23 September 2024

All 42 site photos, by inspection date

Context

Dubai Hills Estate has 20 projects under construction, 45% built on average.

Dubai Hills Estate has 19 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Vida Residences Club Point?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Vida Residences Club Point be completed?
The completion date registered with the Dubai Land Department is February 2029. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Vida Residences Club Point is built?
44%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 6 times since September 2024.
Is Vida Residences Club Point delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of February 2029.
Who is building Vida Residences Club Point?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Vida Residences Club Point?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.