Greenside Residence construction progress
No completion date is registered for Greenside Residence in Dubai Hills Estate yet. At the last site inspection, in November 2026, it was 97% built. The developer is Dubai Hills Estate.
97%
Built, at the site inspection of 19 November 2026
- Finish at recent pace
- December 2026
- Construction started
- November 2023
- First registered
- June 2023
- Developer
- Dubai Hills Estate
- Community
- Dubai Hills Estate
- Units
- 490
- Escrow bank
- Emirates NBD
- Name in Arabic
- جرينسايد ريزيدنس
- Project number
- 2705
- Site inspections
- 10
Schedule
Since February 2026 Greenside Residence has added about 2.7 points a month. At that rate the site reaches 100% around December 2026. No completion date is on record to compare it with.
Site inspections
19 November 2026
97%+3.7 pts
14 September 2026
93%+6.3 pts
4 June 2026
87%+15 pts
13 February 2026
72%+11 pts
13 October 2025
61%+23 pts
14 April 2025
38%+16 pts
2 January 2025
22%+13 pts
21 August 2024
8.7%+7.3 pts
22 March 2024
1.4%+1.4 pts
19 June 2023
0%
Context
Dubai Hills Estate has 19 projects under construction, 44% built on average.
Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Greenside Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Greenside Residence handover date?
- No completion date is on record for Greenside Residence yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Greenside Residence?
- Greenside Residence was 97% built at the site inspection on 19 November 2026. The site has been inspected 10 times since June 2023. The Land Department took 77 site photos at its inspections.
- Who is building Greenside Residence?
- The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for Greenside Residence?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Parkside HillsAlso by Dubai Hills Estate. 68%, Due June 2028.
- Park LaneAlso by Dubai Hills Estate. 55%, Due October 2028.
- Park GateAlso by Dubai Hills Estate. 90%.
- Palace Residences Dubai Hills EstateAlso by Dubai Hills Estate. 51%, Due April 2028.
- Ellington House IVNearby in Dubai Hills Estate. 70%.
- Mallside ResidenceNearby in Dubai Hills Estate. 83%, Due November 2026.
- Soho The BerkeleyNearby in Dubai Hills Estate. 46%, Due October 2026, passed.
- City View Dubai Hills ResidencesNearby in Dubai Hills Estate. 39%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)





.jpeg&w=3840&q=75)