Greenside Residence construction progress
Greenside Residence in Dubai Hills Estate is 93% built at the Land Department inspection of September 2026. Developer Dubai Hills Estate.
93%
Built, at the Land Department site inspection of 14 September 2026
- Finish at recent pace
- November 2026
- Construction started
- November 2023
- Registered with the Land Department
- June 2023
- Developer
- Dubai Hills Estate
- Community
- Dubai Hills Estate
- Units
- 490
- Escrow bank
- Emirates NBD
- Name in Arabic
- جرينسايد ريزيدنس
- Land Department project number
- 2705
- Land Department site inspections
- 9
Schedule
Since October 2025 Greenside Residence has added about 3.0 points a month. At that rate the site reaches 100% around November 2026. The Land Department has no completion date on record to compare it with.
Site inspections
14 September 2026
93%+6.3 pts
4 June 2026
87%+15 pts
13 February 2026
72%+11 pts
13 October 2025
61%+23 pts
14 April 2025
38%+16 pts
2 January 2025
22%+13 pts
21 August 2024
8.7%+7.3 pts
22 March 2024
1.4%+1.4 pts
19 June 2023
0%
Context
Dubai Hills Estate has 20 projects under construction, 45% built on average.
Dubai Hills Estate has 19 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Greenside Residence?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Greenside Residence be completed?
- The Land Department has no completion date on record for Greenside Residence yet.
- How much of Greenside Residence is built?
- 93%, measured at the Land Department site inspection on 14 September 2026. The Land Department engineers have inspected the site 9 times since June 2023.
- Who is building Greenside Residence?
- The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
- Which bank holds the escrow account for Greenside Residence?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Parkside HillsAlso by Dubai Hills Estate. 68%, Due June 2028.
- Club DriveAlso by Dubai Hills Estate. 75%.
- Park LaneAlso by Dubai Hills Estate. 55%.
- Park GateAlso by Dubai Hills Estate. 90%.
- Ellington House IvNearby in Dubai Hills Estate. 70%.
- Mallside ResidenceNearby in Dubai Hills Estate. 83%, Due November 2026.
- Soho The BerkeleyNearby in Dubai Hills Estate. 46%.
- City View Dubai Hills ResidencesNearby in Dubai Hills Estate. 39%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.









.jpg&w=3840&q=75)
.jpg&w=3840&q=75)


.jpeg&w=3840&q=75)