Greenside Residence construction progress

Greenside Residence in Dubai Hills Estate is 93% built at the Land Department inspection of September 2026. Developer Dubai Hills Estate.

93%

Built, at the Land Department site inspection of 14 September 2026

Finish at recent pace
November 2026
Construction started
November 2023
Registered with the Land Department
June 2023
Units
490
Escrow bank
Emirates NBD
Name in Arabic
جرينسايد ريزيدنس
Land Department project number
2705
Land Department site inspections
9

Schedule

Since October 2025 Greenside Residence has added about 3.0 points a month. At that rate the site reaches 100% around November 2026. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

14 September 2026

93%+6.3 pts

  • Greenside Residence construction site, Land Department inspection photo 1, 14 September 2026
  • Greenside Residence construction site, Land Department inspection photo 2, 14 September 2026
  • Greenside Residence construction site, Land Department inspection photo 3, 14 September 2026
  • Greenside Residence construction site, Land Department inspection photo 4, 14 September 2026

4 June 2026

87%+15 pts

  • Greenside Residence construction site, Land Department inspection photo 1, 4 June 2026
  • Greenside Residence construction site, Land Department inspection photo 2, 4 June 2026
  • Greenside Residence construction site, Land Department inspection photo 3, 4 June 2026
  • Greenside Residence construction site, Land Department inspection photo 4, 4 June 2026

13 February 2026

72%+11 pts

  • Greenside Residence construction site, Land Department inspection photo 1, 13 February 2026
  • Greenside Residence construction site, Land Department inspection photo 2, 13 February 2026
  • Greenside Residence construction site, Land Department inspection photo 3, 13 February 2026
  • Greenside Residence construction site, Land Department inspection photo 4, 13 February 2026

13 October 2025

61%+23 pts

  • Greenside Residence construction site, Land Department inspection photo 1, 13 October 2025
  • Greenside Residence construction site, Land Department inspection photo 2, 13 October 2025
  • Greenside Residence construction site, Land Department inspection photo 3, 13 October 2025
  • Greenside Residence construction site, Land Department inspection photo 4, 13 October 2025

14 April 2025

38%+16 pts

  • Greenside Residence construction site, Land Department inspection photo 1, 14 April 2025
  • Greenside Residence construction site, Land Department inspection photo 2, 14 April 2025
  • Greenside Residence construction site, Land Department inspection photo 3, 14 April 2025
  • Greenside Residence construction site, Land Department inspection photo 4, 14 April 2025

2 January 2025

22%+13 pts

  • Greenside Residence construction site, Land Department inspection photo 1, 2 January 2025
  • Greenside Residence construction site, Land Department inspection photo 2, 2 January 2025
  • Greenside Residence construction site, Land Department inspection photo 3, 2 January 2025
  • Greenside Residence construction site, Land Department inspection photo 4, 2 January 2025

21 August 2024

8.7%+7.3 pts

  • Greenside Residence construction site, Land Department inspection photo 1, 21 August 2024
  • Greenside Residence construction site, Land Department inspection photo 2, 21 August 2024
  • Greenside Residence construction site, Land Department inspection photo 3, 21 August 2024
  • Greenside Residence construction site, Land Department inspection photo 4, 21 August 2024

22 March 2024

1.4%+1.4 pts

  • Greenside Residence construction site, Land Department inspection photo 1, 22 March 2024
  • Greenside Residence construction site, Land Department inspection photo 2, 22 March 2024
  • Greenside Residence construction site, Land Department inspection photo 3, 22 March 2024
  • Greenside Residence construction site, Land Department inspection photo 4, 22 March 2024

19 June 2023

0%

  • Greenside Residence construction site, Land Department inspection photo 1, 19 June 2023
  • Greenside Residence construction site, Land Department inspection photo 2, 19 June 2023

All 67 site photos, by inspection date

Context

Dubai Hills Estate has 20 projects under construction, 45% built on average.

Dubai Hills Estate has 19 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Greenside Residence?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Greenside Residence be completed?
The Land Department has no completion date on record for Greenside Residence yet.
How much of Greenside Residence is built?
93%, measured at the Land Department site inspection on 14 September 2026. The Land Department engineers have inspected the site 9 times since June 2023.
Who is building Greenside Residence?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Greenside Residence?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.