Parkland construction progress

The registered completion date for Parkland in Dubai Hills Estate is November 2028. At the last site inspection, in June 2026, it was 50% built. The developer is Dubai Hills Estate.

50%

Built, at the site inspection of 22 June 2026

On pace for its date

Registered completion date
November 2028
Finish at recent pace
September 2027
Construction started
November 2024
First registered
July 2024
Units
209
Escrow bank
Mashreq Bank
Name in Arabic
بارك لاند
Project number
3139
Site inspections
6

Schedule

Since September 2025 Parkland has added about 3.5 points a month. That puts 100% around September 2027, within three months of its registered completion date of November 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 June 2026

50%+19 pts

  • Parkland construction site, inspection photo 1, 22 June 2026
  • Parkland construction site, inspection photo 2, 22 June 2026
  • Parkland construction site, inspection photo 3, 22 June 2026
  • Parkland construction site, inspection photo 4, 22 June 2026

12 February 2026

31%+14 pts

  • Parkland construction site, inspection photo 1, 12 February 2026
  • Parkland construction site, inspection photo 2, 12 February 2026
  • Parkland construction site, inspection photo 3, 12 February 2026
  • Parkland construction site, inspection photo 4, 12 February 2026

3 September 2025

17%+6.6 pts

  • Parkland construction site, inspection photo 1, 3 September 2025
  • Parkland construction site, inspection photo 2, 3 September 2025
  • Parkland construction site, inspection photo 3, 3 September 2025
  • Parkland construction site, inspection photo 4, 3 September 2025

21 May 2025

10.0%+4.8 pts

  • Parkland construction site, inspection photo 1, 21 May 2025
  • Parkland construction site, inspection photo 2, 21 May 2025
  • Parkland construction site, inspection photo 3, 21 May 2025
  • Parkland construction site, inspection photo 4, 21 May 2025

16 December 2024

5.2%+5.2 pts

  • Parkland construction site, inspection photo 1, 16 December 2024
  • Parkland construction site, inspection photo 2, 16 December 2024
  • Parkland construction site, inspection photo 3, 16 December 2024
  • Parkland construction site, inspection photo 4, 16 December 2024

12 June 2024

0%

  • Parkland construction site, inspection photo 1, 12 June 2024
  • Parkland construction site, inspection photo 2, 12 June 2024

All 34 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Parkland?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Parkland handover date?
The registered completion date is November 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Parkland?
Parkland was 50% built at the site inspection on 22 June 2026. The site has been inspected 6 times since June 2024. The Land Department took 34 site photos at its inspections.
Is Parkland delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2028.
Who is building Parkland?
The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Parkland?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.