Parkland construction progress
The registered completion date for Parkland in Dubai Hills Estate is November 2028. At the last site inspection, in June 2026, it was 50% built. The developer is Dubai Hills Estate.
50%
Built, at the site inspection of 22 June 2026
On pace for its date
- Registered completion date
- November 2028
- Finish at recent pace
- September 2027
- Construction started
- November 2024
- First registered
- July 2024
- Developer
- Dubai Hills Estate
- Community
- Dubai Hills Estate
- Units
- 209
- Escrow bank
- Mashreq Bank
- Name in Arabic
- بارك لاند
- Project number
- 3139
- Site inspections
- 6
Schedule
Since September 2025 Parkland has added about 3.5 points a month. That puts 100% around September 2027, within three months of its registered completion date of November 2028.
Site inspections
22 June 2026
50%+19 pts
12 February 2026
31%+14 pts
3 September 2025
17%+6.6 pts
21 May 2025
10.0%+4.8 pts
16 December 2024
5.2%+5.2 pts
12 June 2024
0%
Context
Dubai Hills Estate has 19 projects under construction, 44% built on average.
Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Parkland?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Parkland handover date?
- The registered completion date is November 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Parkland?
- Parkland was 50% built at the site inspection on 22 June 2026. The site has been inspected 6 times since June 2024. The Land Department took 34 site photos at its inspections.
- Is Parkland delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2028.
- Who is building Parkland?
- The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for Parkland?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Greenside ResidenceAlso by Dubai Hills Estate. 97%.
- Parkside HillsAlso by Dubai Hills Estate. 68%, Due June 2028.
- Park LaneAlso by Dubai Hills Estate. 55%, Due October 2028.
- Park GateAlso by Dubai Hills Estate. 90%.
- Ellington House IVNearby in Dubai Hills Estate. 70%.
- Mallside ResidenceNearby in Dubai Hills Estate. 83%, Due November 2026.
- Soho The BerkeleyNearby in Dubai Hills Estate. 46%, Due October 2026, passed.
- City View Dubai Hills ResidencesNearby in Dubai Hills Estate. 39%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.












.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)