Park Lane construction progress
The registered completion date for Park Lane in Dubai Hills Estate is October 2028. At the last site inspection, in May 2026, it was 55% built. The developer is Dubai Hills Estate.
55%
Built, at the site inspection of 22 May 2026
On pace for its date
- Registered completion date
- October 2028
- Finish at recent pace
- August 2027
- Construction started
- January 2024
- First registered
- October 2023
- Developer
- Dubai Hills Estate
- Community
- Dubai Hills Estate
- Units
- 854
- Escrow bank
- Emirates NBD
- Name in Arabic
- بارك لين
- Project number
- 2775
- Site inspections
- 7
Schedule
Since May 2025 Park Lane has added about 3.1 points a month. That puts 100% around August 2027, within three months of its registered completion date of October 2028.
Site inspections
22 May 2026
55%+9.5 pts
6 January 2026
46%+12 pts
10 September 2025
33%+15 pts
29 May 2025
19%+15 pts
11 November 2024
4.3%+4.3 pts
8 May 2024
0%+0.0 pts
25 September 2023
0%
Context
Dubai Hills Estate has 19 projects under construction, 44% built on average.
Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Park Lane?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Park Lane handover date?
- The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Park Lane?
- Park Lane was 55% built at the site inspection on 22 May 2026. The site has been inspected 7 times since September 2023. The Land Department took 55 site photos at its inspections.
- Is Park Lane delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of October 2028.
- Who is building Park Lane?
- The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for Park Lane?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Greenside ResidenceAlso by Dubai Hills Estate. 97%.
- Parkside HillsAlso by Dubai Hills Estate. 68%, Due June 2028.
- Park GateAlso by Dubai Hills Estate. 90%.
- Palace Residences Dubai Hills EstateAlso by Dubai Hills Estate. 51%, Due April 2028.
- Ellington House IVNearby in Dubai Hills Estate. 70%.
- Mallside ResidenceNearby in Dubai Hills Estate. 83%, Due November 2026.
- Soho The BerkeleyNearby in Dubai Hills Estate. 46%, Due October 2026, passed.
- City View Dubai Hills ResidencesNearby in Dubai Hills Estate. 39%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)