Park Lane construction progress

The registered completion date for Park Lane in Dubai Hills Estate is October 2028. At the last site inspection, in May 2026, it was 55% built. The developer is Dubai Hills Estate.

55%

Built, at the site inspection of 22 May 2026

On pace for its date

Registered completion date
October 2028
Finish at recent pace
August 2027
Construction started
January 2024
First registered
October 2023
Units
854
Escrow bank
Emirates NBD
Name in Arabic
بارك لين
Project number
2775
Site inspections
7

Schedule

Since May 2025 Park Lane has added about 3.1 points a month. That puts 100% around August 2027, within three months of its registered completion date of October 2028.

0%25%50%75%100%20242025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 May 2026

55%+9.5 pts

  • Park Lane construction site, inspection photo 1, 22 May 2026
  • Park Lane construction site, inspection photo 2, 22 May 2026
  • Park Lane construction site, inspection photo 3, 22 May 2026
  • Park Lane construction site, inspection photo 4, 22 May 2026

6 January 2026

46%+12 pts

  • Park Lane construction site, inspection photo 1, 6 January 2026
  • Park Lane construction site, inspection photo 2, 6 January 2026
  • Park Lane construction site, inspection photo 3, 6 January 2026
  • Park Lane construction site, inspection photo 4, 6 January 2026

10 September 2025

33%+15 pts

  • Park Lane construction site, inspection photo 1, 10 September 2025
  • Park Lane construction site, inspection photo 2, 10 September 2025
  • Park Lane construction site, inspection photo 3, 10 September 2025
  • Park Lane construction site, inspection photo 4, 10 September 2025

29 May 2025

19%+15 pts

  • Park Lane construction site, inspection photo 1, 29 May 2025
  • Park Lane construction site, inspection photo 2, 29 May 2025
  • Park Lane construction site, inspection photo 3, 29 May 2025
  • Park Lane construction site, inspection photo 4, 29 May 2025

11 November 2024

4.3%+4.3 pts

  • Park Lane construction site, inspection photo 1, 11 November 2024
  • Park Lane construction site, inspection photo 2, 11 November 2024
  • Park Lane construction site, inspection photo 3, 11 November 2024
  • Park Lane construction site, inspection photo 4, 11 November 2024

8 May 2024

0%+0.0 pts

  • Park Lane construction site, inspection photo 1, 8 May 2024
  • Park Lane construction site, inspection photo 2, 8 May 2024
  • Park Lane construction site, inspection photo 3, 8 May 2024

25 September 2023

0%

  • Park Lane construction site, inspection photo 1, 25 September 2023
  • Park Lane construction site, inspection photo 2, 25 September 2023
  • Park Lane construction site, inspection photo 3, 25 September 2023
  • Park Lane construction site, inspection photo 4, 25 September 2023

All 55 site photos, by inspection date

Context

Dubai Hills Estate has 19 projects under construction, 44% built on average.

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Park Lane?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Park Lane handover date?
The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Park Lane?
Park Lane was 55% built at the site inspection on 22 May 2026. The site has been inspected 7 times since September 2023. The Land Department took 55 site photos at its inspections.
Is Park Lane delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of October 2028.
Who is building Park Lane?
The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Park Lane?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.