Greencrest construction progress
Greencrest is 1.2% built at the Land Department inspection of May 2026. Developer Dubai Hills Estate. Completion registered for June 2029.
1.2%
Built, at the Land Department site inspection of 7 May 2026
Running behind its date
- Completion date (Land Department)
- June 2029
- Finish at recent pace
- June 2073
- Construction started
- November 2025
- Registered with the Land Department
- October 2025
- Developer
- Dubai Hills Estate
- Units
- 195
- Escrow bank
- Mashreq Bank
- Name in Arabic
- جرينكرست
- Land Department project number
- 4136
- Land Department site inspections
- 2
Schedule
Between October 2025 and May 2026 the site added about 0.2 points a month. At that rate it would finish around June 2073, more than three months after the June 2029 date registered with the Land Department.
Site inspections
7 May 2026
1.2%+1.2 pts
10 October 2025
0%
Context
Dubai Hills Estate has 19 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Greencrest?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Greencrest be completed?
- The completion date registered with the Dubai Land Department is June 2029. At the pace of its recent inspections the site would reach 100% around June 2073. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Greencrest is built?
- 1.2%, measured at the Land Department site inspection on 7 May 2026. The Land Department engineers have inspected the site 2 times since October 2025.
- Is Greencrest delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
- Who is building Greencrest?
- The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
- Which bank holds the escrow account for Greencrest?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Greenside ResidenceAlso by Dubai Hills Estate. 93%.
- Parkside HillsAlso by Dubai Hills Estate. 68%, Due June 2028.
- Club DriveAlso by Dubai Hills Estate. 75%.
- Park LaneAlso by Dubai Hills Estate. 55%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.