Greencrest construction progress

The registered completion date for Greencrest is June 2029. At the last site inspection, in May 2026, it was 1.2% built. The developer is Dubai Hills Estate.

1.2%

Built, at the site inspection of 7 May 2026

Running behind its date

Registered completion date
June 2029
Finish at recent pace
June 2073
Construction started
November 2025
First registered
October 2025
Units
195
Escrow bank
Mashreq Bank
Name in Arabic
جرينكرست
Project number
4136
Site inspections
2

Schedule

Between October 2025 and May 2026 the site added about 0.2 points a month. At that rate it would finish around June 2073, more than three months after its registered date of June 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 May 2026

1.2%+1.2 pts

  • Greencrest construction site, inspection photo 1, 7 May 2026
  • Greencrest construction site, inspection photo 2, 7 May 2026

10 October 2025

0%

  • Greencrest construction site, inspection photo 1, 10 October 2025
  • Greencrest construction site, inspection photo 2, 10 October 2025

All 4 site photos, by inspection date

Context

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Greencrest?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Greencrest handover date?
The registered completion date is June 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2073. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Greencrest?
Greencrest was 1.2% built at the site inspection on 7 May 2026. The site has been inspected 2 times since October 2025. The Land Department took 4 site photos at its inspections.
Is Greencrest delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
Who is building Greencrest?
The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for Greencrest?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.