Palace Residences Hillside A construction progress
The registered completion date for Palace Residences Hillside A in Dubai Hills Estate is June 2029. At the last site inspection, in May 2026, it was 7.9% built. The developer is Dubai Hills Estate.
16%
Built, at the site inspection of 5 May 2026
Running behind its date
- Registered completion date
- June 2029
- Finish at recent pace
- April 2035
- Construction started
- September 2025
- First registered
- August 2025
- Developer
- Dubai Hills Estate
- Community
- Dubai Hills Estate
- Units
- 360
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- A بالاس رزيدنسز هيلسايد
- Project number
- 4015
- Site inspections
- 3
Schedule
Between July 2025 and May 2026 the site added about 0.9 points a month. At that rate it would finish around April 2035, more than three months after its registered date of June 2029.
Site inspections
5 May 2026
7.9%+2.1 pts
19 January 2026
5.8%+5.8 pts
31 July 2025
0%
Context
Dubai Hills Estate has 19 projects under construction, 44% built on average.
Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Palace Residences Hillside A?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Palace Residences Hillside A handover date?
- The registered completion date is June 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Palace Residences Hillside A?
- Palace Residences Hillside A was 16% built at the site inspection on 5 May 2026. The site has been inspected 3 times since July 2025. The Land Department took 8 site photos at its inspections.
- Is Palace Residences Hillside A delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
- Who is building Palace Residences Hillside A?
- The registered developer is Dubai Hills Estate. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for Palace Residences Hillside A?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Greenside ResidenceAlso by Dubai Hills Estate. 97%.
- Parkside HillsAlso by Dubai Hills Estate. 68%, Due June 2028.
- Park LaneAlso by Dubai Hills Estate. 55%, Due October 2028.
- Park GateAlso by Dubai Hills Estate. 90%.
- Ellington House IVNearby in Dubai Hills Estate. 70%.
- Mallside ResidenceNearby in Dubai Hills Estate. 83%, Due November 2026.
- Soho The BerkeleyNearby in Dubai Hills Estate. 46%, Due October 2026, passed.
- City View Dubai Hills ResidencesNearby in Dubai Hills Estate. 39%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.