Off-plan projects in Dubai Marina

13 projects in Dubai Marina are under construction. On average they are 46% built. 3 have passed their registered completion date. The next one due is Liv Lux, in December 2026.

Questions

How many off-plan projects are under construction in Dubai Marina?

13 projects are under construction in Dubai Marina, 46% built on average at the latest site inspections.

Which Dubai Marina projects are due to finish next?

By registered completion date: Liv Lux (December 2026, 87% built), Marina Shores (December 2026, 87% built) and Bluewaters Bay (March 2027, 37% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.

How many Dubai Marina projects are past their completion date?

3 of 13, among them Pier 8, Pelagos By Igo and Residences Du Port, Dubai Marina, Autograph Collection Residences. A project counts as late once its registered completion date has passed before it reaches 100%.

Which developers are building in Dubai Marina?

13 developers are building here, each with one project.

Reading these figures

Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.

What happens at handover and how to snag a new home cover the steps after 100%.

Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.