Residences Du Port, Dubai Marina, Autograph Collection Residences construction progress
Residences Du Port, Dubai Marina, Autograph Collection Residences in Dubai Marina is 71% built at the Land Department inspection of July 2026. Developer Prime Marina Property Developers. Completion registered for June 2026.
71%
Built, at the Land Department site inspection of 17 July 2026
4 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- September 2032
- Construction started
- June 2025
- Registered with the Land Department
- June 2025
- Developer
- Prime Marina Property Developers
- Community
- Dubai Marina
- Units
- 74
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- ريزيدنسز دو بورت، دبي مارينا، أوتوجراف كوليكشن ريزيدنسز
- Land Department project number
- 3762
- Land Department site inspections
- 4
Schedule
Residences Du Port, Dubai Marina, Autograph Collection Residences was registered to complete in June 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 0.4 points a month. Kept at that rate, the site would reach 100% around September 2032.
Site inspections
17 July 2026
71%+0.9 pts
2 April 2026
70%+2.0 pts
3 December 2025
68%+1.8 pts
20 May 2025
66%
Context
Dubai Marina has 13 projects under construction, 44% built on average.
Own a unit in Residences Du Port, Dubai Marina, Autograph Collection Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Residences Du Port, Dubai Marina, Autograph Collection Residences be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around September 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Residences Du Port, Dubai Marina, Autograph Collection Residences is built?
- 71%, measured at the Land Department site inspection on 17 July 2026. The Land Department engineers have inspected the site 4 times since May 2025.
- Is Residences Du Port, Dubai Marina, Autograph Collection Residences delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Residences Du Port, Dubai Marina, Autograph Collection Residences?
- The registered developer is Prime Marina Property Developers.
- Which bank holds the escrow account for Residences Du Port, Dubai Marina, Autograph Collection Residences?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Pier 8Nearby in Dubai Marina. 70%, Due March 2026, passed.
- Marina ShoresNearby in Dubai Marina. 87%, Due December 2026.
- Liv LuxNearby in Dubai Marina. 79%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.