Pelagos By Igo construction progress

Pelagos By Igo in Dubai Marina is 84% built at the Land Department inspection of April 2026. Developer Digo Real Estate Development (Br Of Invest Group Overseas ). Completion registered for March 2026.

84%

Built, at the Land Department site inspection of 30 April 2026

6 months past its registered completion date

Completion date (Land Department)
March 2026
Finish at recent pace
January 2027
Construction started
December 2024
Registered with the Land Department
October 2024
Community
Dubai Marina
Units
296
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بيلاغوس باي أي جي أو
Land Department project number
3246
Land Department site inspections
5

Schedule

Pelagos By Igo was registered to complete in March 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 1.8 points a month. Kept at that rate, the site would reach 100% around January 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 April 2026

84%+3.8 pts

  • Pelagos By Igo construction site, Land Department inspection photo 1, 30 April 2026
  • Pelagos By Igo construction site, Land Department inspection photo 2, 30 April 2026
  • Pelagos By Igo construction site, Land Department inspection photo 3, 30 April 2026
  • Pelagos By Igo construction site, Land Department inspection photo 4, 30 April 2026

19 January 2026

80%+9.3 pts

  • Pelagos By Igo construction site, Land Department inspection photo 1, 19 January 2026
  • Pelagos By Igo construction site, Land Department inspection photo 2, 19 January 2026
  • Pelagos By Igo construction site, Land Department inspection photo 3, 19 January 2026
  • Pelagos By Igo construction site, Land Department inspection photo 4, 19 January 2026

25 September 2025

71%+1.2 pts

  • Pelagos By Igo construction site, Land Department inspection photo 1, 25 September 2025
  • Pelagos By Igo construction site, Land Department inspection photo 2, 25 September 2025
  • Pelagos By Igo construction site, Land Department inspection photo 3, 25 September 2025
  • Pelagos By Igo construction site, Land Department inspection photo 4, 25 September 2025

18 March 2025

70%+0.8 pts

  • Pelagos By Igo construction site, Land Department inspection photo 1, 18 March 2025
  • Pelagos By Igo construction site, Land Department inspection photo 2, 18 March 2025
  • Pelagos By Igo construction site, Land Department inspection photo 3, 18 March 2025
  • Pelagos By Igo construction site, Land Department inspection photo 4, 18 March 2025

6 September 2024

69%

  • Pelagos By Igo construction site, Land Department inspection photo 1, 6 September 2024
  • Pelagos By Igo construction site, Land Department inspection photo 2, 6 September 2024
  • Pelagos By Igo construction site, Land Department inspection photo 3, 6 September 2024
  • Pelagos By Igo construction site, Land Department inspection photo 4, 6 September 2024

All 48 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 44% built on average.

Digo Real Estate Development (Br Of Invest Group Overseas ) has 5 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Pelagos By Igo?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Pelagos By Igo be completed?
The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Pelagos By Igo is built?
84%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 5 times since September 2024.
Is Pelagos By Igo delayed?
Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
Who is building Pelagos By Igo?
The registered developer is Digo Real Estate Development (Br Of Invest Group Overseas ). It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Pelagos By Igo?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.