Pelagos By Igo construction progress
Pelagos By Igo in Dubai Marina is 84% built at the Land Department inspection of April 2026. Developer Digo Real Estate Development (Br Of Invest Group Overseas ). Completion registered for March 2026.
84%
Built, at the Land Department site inspection of 30 April 2026
6 months past its registered completion date
- Completion date (Land Department)
- March 2026
- Finish at recent pace
- January 2027
- Construction started
- December 2024
- Registered with the Land Department
- October 2024
- Community
- Dubai Marina
- Units
- 296
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- بيلاغوس باي أي جي أو
- Land Department project number
- 3246
- Land Department site inspections
- 5
Schedule
Pelagos By Igo was registered to complete in March 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 1.8 points a month. Kept at that rate, the site would reach 100% around January 2027.
Site inspections
30 April 2026
84%+3.8 pts
19 January 2026
80%+9.3 pts
25 September 2025
71%+1.2 pts
18 March 2025
70%+0.8 pts
6 September 2024
69%
Context
Dubai Marina has 13 projects under construction, 44% built on average.
Digo Real Estate Development (Br Of Invest Group Overseas ) has 5 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Pelagos By Igo?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Pelagos By Igo be completed?
- The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Pelagos By Igo is built?
- 84%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 5 times since September 2024.
- Is Pelagos By Igo delayed?
- Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
- Who is building Pelagos By Igo?
- The registered developer is Digo Real Estate Development (Br Of Invest Group Overseas ). It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Pelagos By Igo?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azura ResidencesAlso by Digo Real Estate Development (Br Of Invest Group Overseas ). 69%.
- Ayaan Heights IAlso by Digo Real Estate Development (Br Of Invest Group Overseas ). 20%.
- The WinslowAlso by Digo Real Estate Development (Br Of Invest Group Overseas ). 0%, Due June 2028.
- The Mansions By MagAlso by Digo Real Estate Development (Br Of Invest Group Overseas ). 9.3%, Due April 2027.
- Pier 8Nearby in Dubai Marina. 70%, Due March 2026, passed.
- Marina ShoresNearby in Dubai Marina. 87%, Due December 2026.
- Liv LuxNearby in Dubai Marina. 79%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)