Pier 8 construction progress

Pier 8 in Dubai Marina was registered to complete in March 2026 and is still under construction. At the last site inspection, in November 2026, it was 93% built. The developer is Pier 8 Real Estate Development.

93%

Built, at the site inspection of 11 November 2026

9 months past its registered completion date

Registered completion date
March 2026
Finish at recent pace
September 2027
Construction started
April 2022
First registered
March 2023
Developer
Pier 8 Real Estate Development
Community
Dubai Marina
Units
341
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بيير 8
Project number
2380
Site inspections
3

Schedule

Pier 8 was registered to complete in March 2026, 9 months ago, and is still under construction. Over the last year of inspections it has added about 0.7 points a month. Kept at that rate, the site would reach 100% around September 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 November 2026

93%+23 pts

  • Pier 8 construction site, inspection photo 1, 11 November 2026
  • Pier 8 construction site, inspection photo 2, 11 November 2026
  • Pier 8 construction site, inspection photo 3, 11 November 2026
  • Pier 8 construction site, inspection photo 4, 11 November 2026

14 February 2024

70%+13 pts

  • Pier 8 construction site, inspection photo 1, 14 February 2024
  • Pier 8 construction site, inspection photo 2, 14 February 2024
  • Pier 8 construction site, inspection photo 3, 14 February 2024
  • Pier 8 construction site, inspection photo 4, 14 February 2024

11 July 2023

57%

  • Pier 8 construction site, inspection photo 1, 11 July 2023
  • Pier 8 construction site, inspection photo 2, 11 July 2023
  • Pier 8 construction site, inspection photo 3, 11 July 2023
  • Pier 8 construction site, inspection photo 4, 11 July 2023

All 29 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 46% built on average.

Own a unit in Pier 8?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Pier 8 handover date?
The registered completion date was March 2026, and the register still lists Pier 8 as under construction. At the pace of its recent inspections the site would reach 100% around September 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Pier 8?
Pier 8 was 93% built at the site inspection on 11 November 2026. The site has been inspected 3 times since July 2023. The Land Department took 29 site photos at its inspections.
Is Pier 8 delayed?
Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
Who is building Pier 8?
The registered developer is Pier 8 Real Estate Development.
Which bank holds the escrow account for Pier 8?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.