Pier 8 construction progress
Pier 8 in Dubai Marina was registered to complete in March 2026 and is still under construction. At the last site inspection, in November 2026, it was 93% built. The developer is Pier 8 Real Estate Development.
93%
Built, at the site inspection of 11 November 2026
9 months past its registered completion date
- Registered completion date
- March 2026
- Finish at recent pace
- September 2027
- Construction started
- April 2022
- First registered
- March 2023
- Developer
- Pier 8 Real Estate Development
- Community
- Dubai Marina
- Units
- 341
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- بيير 8
- Project number
- 2380
- Site inspections
- 3
Schedule
Pier 8 was registered to complete in March 2026, 9 months ago, and is still under construction. Over the last year of inspections it has added about 0.7 points a month. Kept at that rate, the site would reach 100% around September 2027.
Site inspections
11 November 2026
93%+23 pts
14 February 2024
70%+13 pts
11 July 2023
57%
Context
Dubai Marina has 13 projects under construction, 46% built on average.
Own a unit in Pier 8?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Pier 8 handover date?
- The registered completion date was March 2026, and the register still lists Pier 8 as under construction. At the pace of its recent inspections the site would reach 100% around September 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Pier 8?
- Pier 8 was 93% built at the site inspection on 11 November 2026. The site has been inspected 3 times since July 2023. The Land Department took 29 site photos at its inspections.
- Is Pier 8 delayed?
- Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
- Who is building Pier 8?
- The registered developer is Pier 8 Real Estate Development.
- Which bank holds the escrow account for Pier 8?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Marina ShoresNearby in Dubai Marina. 87%, Due December 2026.
- Liv LuxNearby in Dubai Marina. 87%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Aeternitas TowerNearby in Dubai Marina. 58%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)