Pier 8 construction progress

Pier 8 in Dubai Marina is 70% built at the Land Department inspection of February 2024. Developer Pier 8 Real Estate Development. Completion registered for March 2026.

70%

Built, at the Land Department site inspection of 14 February 2024

7 months past its registered completion date

Completion date (Land Department)
March 2026
Finish at recent pace
June 2025
Construction started
April 2022
Registered with the Land Department
March 2023
Developer
Pier 8 Real Estate Development
Community
Dubai Marina
Units
341
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بيير 8
Land Department project number
2380
Land Department site inspections
2

Schedule

Pier 8 was registered to complete in March 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 1.8 points a month. Kept at that rate, the site would reach 100% around June 2025.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 February 2024

70%+13 pts

  • Pier 8 construction site, Land Department inspection photo 1, 14 February 2024
  • Pier 8 construction site, Land Department inspection photo 2, 14 February 2024
  • Pier 8 construction site, Land Department inspection photo 3, 14 February 2024
  • Pier 8 construction site, Land Department inspection photo 4, 14 February 2024

11 July 2023

57%

  • Pier 8 construction site, Land Department inspection photo 1, 11 July 2023
  • Pier 8 construction site, Land Department inspection photo 2, 11 July 2023
  • Pier 8 construction site, Land Department inspection photo 3, 11 July 2023
  • Pier 8 construction site, Land Department inspection photo 4, 11 July 2023

All 17 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 44% built on average.

Own a unit in Pier 8?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Pier 8 be completed?
The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around June 2025. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Pier 8 is built?
70%, measured at the Land Department site inspection on 14 February 2024. The Land Department engineers have inspected the site 2 times since July 2023.
Is Pier 8 delayed?
Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
Who is building Pier 8?
The registered developer is Pier 8 Real Estate Development.
Which bank holds the escrow account for Pier 8?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.