Aba Lux Living construction progress

Aba Lux Living in Dubai Marina is 6.9% built at the Land Department inspection of September 2026. Developer A B A Real Estate Development.

6.9%

Built, at the Land Department site inspection of 7 September 2026

Finish at recent pace
June 2050
Construction started
April 2024
Registered with the Land Department
April 2024
Developer
A B A Real Estate Development
Community
Dubai Marina
Units
419
Escrow bank
Sharjah Islamic Bank
Name in Arabic
أبا لوكس ليفينج
Land Department project number
2939
Land Department site inspections
7

Schedule

Since September 2025 Aba Lux Living has added about 0.3 points a month. At that rate the site reaches 100% around June 2050. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%20252026
Progress at each Land Department site inspection

Site inspections

7 September 2026

6.9%+1.0 pts

  • Aba Lux Living construction site, Land Department inspection photo 1, 7 September 2026
  • Aba Lux Living construction site, Land Department inspection photo 2, 7 September 2026
  • Aba Lux Living construction site, Land Department inspection photo 3, 7 September 2026
  • Aba Lux Living construction site, Land Department inspection photo 4, 7 September 2026

4 June 2026

5.8%+2.1 pts

  • Aba Lux Living construction site, Land Department inspection photo 1, 4 June 2026
  • Aba Lux Living construction site, Land Department inspection photo 2, 4 June 2026
  • Aba Lux Living construction site, Land Department inspection photo 3, 4 June 2026
  • Aba Lux Living construction site, Land Department inspection photo 4, 4 June 2026

3 March 2026

3.8%+0.8 pts

  • Aba Lux Living construction site, Land Department inspection photo 1, 3 March 2026
  • Aba Lux Living construction site, Land Department inspection photo 2, 3 March 2026

8 September 2025

3.0%+1.8 pts

  • Aba Lux Living construction site, Land Department inspection photo 1, 8 September 2025
  • Aba Lux Living construction site, Land Department inspection photo 2, 8 September 2025
  • Aba Lux Living construction site, Land Department inspection photo 3, 8 September 2025

26 May 2025

1.2%+1.2 pts

  • Aba Lux Living construction site, Land Department inspection photo 1, 26 May 2025
  • Aba Lux Living construction site, Land Department inspection photo 2, 26 May 2025
  • Aba Lux Living construction site, Land Department inspection photo 3, 26 May 2025

10 September 2024

0%

  • Aba Lux Living construction site, Land Department inspection photo 1, 10 September 2024
  • Aba Lux Living construction site, Land Department inspection photo 2, 10 September 2024

16 February 2024

0%

  • Aba Lux Living construction site, Land Department inspection photo 1, 16 February 2024
  • Aba Lux Living construction site, Land Department inspection photo 2, 16 February 2024

All 22 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 44% built on average.

Own a unit in Aba Lux Living?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Aba Lux Living be completed?
The Land Department has no completion date on record for Aba Lux Living yet.
How much of Aba Lux Living is built?
6.9%, measured at the Land Department site inspection on 7 September 2026. The Land Department engineers have inspected the site 7 times since February 2024.
Who is building Aba Lux Living?
The registered developer is A B A Real Estate Development.
Which bank holds the escrow account for Aba Lux Living?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.