The Residences, Al Habtoor Grand construction progress
No completion date is registered for The Residences, Al Habtoor Grand in Dubai Marina yet. At the last site inspection, in June 2026, it was 35% built. The developer is Al Habtoor City Real Estate Development (Br. Of Dubai National Investment Co.
35%
Built, at the site inspection of 11 June 2026
- Finish at recent pace
- February 2029
- Construction started
- March 2024
- First registered
- January 2024
- Developer
- Al Habtoor City Real Estate Development (Br. Of Dubai National Investment Co
- Community
- Dubai Marina
- Units
- 272
- Escrow bank
- Emirates NBD
- Name in Arabic
- ذا ريزيدنسيز، الحبتور جراند
- Project number
- 2892
- Site inspections
- 5
Schedule
Since June 2025 The Residences, Al Habtoor Grand has added about 2.0 points a month. At that rate the site reaches 100% around February 2029. No completion date is on record to compare it with.
Site inspections
11 June 2026
35%+6.3 pts
9 February 2026
29%+8.9 pts
29 September 2025
20%+8.5 pts
19 June 2025
12%+12 pts
28 December 2023
0%
Context
Dubai Marina has 13 projects under construction, 46% built on average.
Al Habtoor City Real Estate Development (Br. Of Dubai National Investment Co has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Residences, Al Habtoor Grand?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Residences, Al Habtoor Grand handover date?
- No completion date is on record for The Residences, Al Habtoor Grand yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on The Residences, Al Habtoor Grand?
- The Residences, Al Habtoor Grand was 35% built at the site inspection on 11 June 2026. The site has been inspected 5 times since December 2023. The Land Department took 39 site photos at its inspections.
- Who is building The Residences, Al Habtoor Grand?
- The registered developer is Al Habtoor City Real Estate Development (Br. Of Dubai National Investment Co. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for The Residences, Al Habtoor Grand?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Al Habtoor TowerAlso by Al Habtoor City Real Estate Development (Br. Of Dubai National Investment Co. 90%, Due December 2026.
- Pier 8Nearby in Dubai Marina. 93%, Due March 2026, passed.
- Marina ShoresNearby in Dubai Marina. 87%, Due December 2026.
- Liv LuxNearby in Dubai Marina. 87%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)