Marina Shores construction progress
Marina Shores in Dubai Marina is 87% built at the Land Department inspection of May 2026. Developer Emaar Properties. Completion registered for December 2026.
87%
Built, at the Land Department site inspection of 14 May 2026
On pace for its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- September 2026
- Construction started
- December 2022
- Registered with the Land Department
- July 2022
- Developer
- Emaar Properties
- Community
- Dubai Marina
- Units
- 447
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- مارينا شورز
- Land Department project number
- 2425
- Land Department site inspections
- 11
Schedule
Since July 2025 Marina Shores has added about 3.3 points a month. That puts 100% around September 2026, within three months of its registered completion date of December 2026.
Site inspections
14 May 2026
87%+5.3 pts
26 January 2026
82%+15 pts
30 October 2025
67%+12 pts
17 July 2025
54%+11 pts
29 April 2025
43%+9.0 pts
30 December 2024
34%+17 pts
9 September 2024
18%+5.9 pts
22 March 2024
12%+5.6 pts
9 October 2023
6.0%+1.5 pts
20 June 2023
4.5%+3.7 pts
Context
Dubai Marina has 13 projects under construction, 44% built on average.
Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Marina Shores?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Marina Shores be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Marina Shores is built?
- 87%, measured at the Land Department site inspection on 14 May 2026. The Land Department engineers have inspected the site 11 times since February 2023.
- Is Marina Shores delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
- Who is building Marina Shores?
- The registered developer is Emaar Properties. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for Marina Shores?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Oasis - PalmieraAlso by Emaar Properties. 82%.
- The Oasis - MirageAlso by Emaar Properties. 47%.
- The Oasis - Palmiera 2Also by Emaar Properties. 77%.
- The Oasis - Palmiera 3Also by Emaar Properties. 73%, Due October 2028.
- Pier 8Nearby in Dubai Marina. 70%, Due March 2026, passed.
- Liv LuxNearby in Dubai Marina. 79%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Aeternitas TowerNearby in Dubai Marina. 58%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)













.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)