Marina Shores construction progress

The registered completion date for Marina Shores in Dubai Marina is December 2026. At the last site inspection, in May 2026, it was 87% built. The developer is Emaar Properties.

87%

Built, at the site inspection of 14 May 2026

On pace for its date

Registered completion date
December 2026
Finish at recent pace
September 2026
Construction started
December 2022
First registered
July 2022
Community
Dubai Marina
Units
444
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
مارينا شورز
Project number
2425
Site inspections
11

Schedule

Since July 2025 Marina Shores has added about 3.3 points a month. That puts 100% around September 2026, within three months of its registered completion date of December 2026.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 May 2026

87%+5.3 pts

  • Marina Shores construction site, inspection photo 1, 14 May 2026
  • Marina Shores construction site, inspection photo 2, 14 May 2026
  • Marina Shores construction site, inspection photo 3, 14 May 2026
  • Marina Shores construction site, inspection photo 4, 14 May 2026

26 January 2026

82%+15 pts

  • Marina Shores construction site, inspection photo 1, 26 January 2026
  • Marina Shores construction site, inspection photo 2, 26 January 2026
  • Marina Shores construction site, inspection photo 3, 26 January 2026
  • Marina Shores construction site, inspection photo 4, 26 January 2026

30 October 2025

67%+12 pts

  • Marina Shores construction site, inspection photo 1, 30 October 2025
  • Marina Shores construction site, inspection photo 2, 30 October 2025
  • Marina Shores construction site, inspection photo 3, 30 October 2025
  • Marina Shores construction site, inspection photo 4, 30 October 2025

17 July 2025

54%+11 pts

  • Marina Shores construction site, inspection photo 1, 17 July 2025
  • Marina Shores construction site, inspection photo 2, 17 July 2025
  • Marina Shores construction site, inspection photo 3, 17 July 2025
  • Marina Shores construction site, inspection photo 4, 17 July 2025

29 April 2025

43%+9.0 pts

  • Marina Shores construction site, inspection photo 1, 29 April 2025
  • Marina Shores construction site, inspection photo 2, 29 April 2025
  • Marina Shores construction site, inspection photo 3, 29 April 2025
  • Marina Shores construction site, inspection photo 4, 29 April 2025

30 December 2024

34%+17 pts

  • Marina Shores construction site, inspection photo 1, 30 December 2024
  • Marina Shores construction site, inspection photo 2, 30 December 2024
  • Marina Shores construction site, inspection photo 3, 30 December 2024
  • Marina Shores construction site, inspection photo 4, 30 December 2024

9 September 2024

18%+5.9 pts

  • Marina Shores construction site, inspection photo 1, 9 September 2024
  • Marina Shores construction site, inspection photo 2, 9 September 2024
  • Marina Shores construction site, inspection photo 3, 9 September 2024
  • Marina Shores construction site, inspection photo 4, 9 September 2024

22 March 2024

12%+5.6 pts

  • Marina Shores construction site, inspection photo 1, 22 March 2024

9 October 2023

6.0%+1.5 pts

  • Marina Shores construction site, inspection photo 1, 9 October 2023
  • Marina Shores construction site, inspection photo 2, 9 October 2023
  • Marina Shores construction site, inspection photo 3, 9 October 2023
  • Marina Shores construction site, inspection photo 4, 9 October 2023

20 June 2023

4.5%+3.7 pts

  • Marina Shores construction site, inspection photo 1, 20 June 2023
  • Marina Shores construction site, inspection photo 2, 20 June 2023
  • Marina Shores construction site, inspection photo 3, 20 June 2023
  • Marina Shores construction site, inspection photo 4, 20 June 2023

All 78 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 46% built on average.

Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Marina Shores?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Marina Shores handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Marina Shores?
Marina Shores was 87% built at the site inspection on 14 May 2026. The site has been inspected 11 times since February 2023. The Land Department took 78 site photos at its inspections.
Is Marina Shores delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
Who is building Marina Shores?
The registered developer is Emaar Properties. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Marina Shores?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.