Marina Shores construction progress

Marina Shores in Dubai Marina is 87% built at the Land Department inspection of May 2026. Developer Emaar Properties. Completion registered for December 2026.

87%

Built, at the Land Department site inspection of 14 May 2026

On pace for its date

Completion date (Land Department)
December 2026
Finish at recent pace
September 2026
Construction started
December 2022
Registered with the Land Department
July 2022
Community
Dubai Marina
Units
447
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
مارينا شورز
Land Department project number
2425
Land Department site inspections
11

Schedule

Since July 2025 Marina Shores has added about 3.3 points a month. That puts 100% around September 2026, within three months of its registered completion date of December 2026.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 May 2026

87%+5.3 pts

  • Marina Shores construction site, Land Department inspection photo 1, 14 May 2026
  • Marina Shores construction site, Land Department inspection photo 2, 14 May 2026
  • Marina Shores construction site, Land Department inspection photo 3, 14 May 2026
  • Marina Shores construction site, Land Department inspection photo 4, 14 May 2026

26 January 2026

82%+15 pts

  • Marina Shores construction site, Land Department inspection photo 1, 26 January 2026
  • Marina Shores construction site, Land Department inspection photo 2, 26 January 2026
  • Marina Shores construction site, Land Department inspection photo 3, 26 January 2026
  • Marina Shores construction site, Land Department inspection photo 4, 26 January 2026

30 October 2025

67%+12 pts

  • Marina Shores construction site, Land Department inspection photo 1, 30 October 2025
  • Marina Shores construction site, Land Department inspection photo 2, 30 October 2025
  • Marina Shores construction site, Land Department inspection photo 3, 30 October 2025
  • Marina Shores construction site, Land Department inspection photo 4, 30 October 2025

17 July 2025

54%+11 pts

  • Marina Shores construction site, Land Department inspection photo 1, 17 July 2025
  • Marina Shores construction site, Land Department inspection photo 2, 17 July 2025
  • Marina Shores construction site, Land Department inspection photo 3, 17 July 2025
  • Marina Shores construction site, Land Department inspection photo 4, 17 July 2025

29 April 2025

43%+9.0 pts

  • Marina Shores construction site, Land Department inspection photo 1, 29 April 2025
  • Marina Shores construction site, Land Department inspection photo 2, 29 April 2025
  • Marina Shores construction site, Land Department inspection photo 3, 29 April 2025
  • Marina Shores construction site, Land Department inspection photo 4, 29 April 2025

30 December 2024

34%+17 pts

  • Marina Shores construction site, Land Department inspection photo 1, 30 December 2024
  • Marina Shores construction site, Land Department inspection photo 2, 30 December 2024
  • Marina Shores construction site, Land Department inspection photo 3, 30 December 2024
  • Marina Shores construction site, Land Department inspection photo 4, 30 December 2024

9 September 2024

18%+5.9 pts

  • Marina Shores construction site, Land Department inspection photo 1, 9 September 2024
  • Marina Shores construction site, Land Department inspection photo 2, 9 September 2024
  • Marina Shores construction site, Land Department inspection photo 3, 9 September 2024
  • Marina Shores construction site, Land Department inspection photo 4, 9 September 2024

22 March 2024

12%+5.6 pts

  • Marina Shores construction site, Land Department inspection photo 1, 22 March 2024

9 October 2023

6.0%+1.5 pts

  • Marina Shores construction site, Land Department inspection photo 1, 9 October 2023
  • Marina Shores construction site, Land Department inspection photo 2, 9 October 2023
  • Marina Shores construction site, Land Department inspection photo 3, 9 October 2023
  • Marina Shores construction site, Land Department inspection photo 4, 9 October 2023

20 June 2023

4.5%+3.7 pts

  • Marina Shores construction site, Land Department inspection photo 1, 20 June 2023
  • Marina Shores construction site, Land Department inspection photo 2, 20 June 2023
  • Marina Shores construction site, Land Department inspection photo 3, 20 June 2023
  • Marina Shores construction site, Land Department inspection photo 4, 20 June 2023

All 78 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 44% built on average.

Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Marina Shores?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Marina Shores be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Marina Shores is built?
87%, measured at the Land Department site inspection on 14 May 2026. The Land Department engineers have inspected the site 11 times since February 2023.
Is Marina Shores delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
Who is building Marina Shores?
The registered developer is Emaar Properties. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Marina Shores?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.