Six Senses Residences Dubai Marina construction progress
No completion date is registered for Six Senses Residences Dubai Marina in Dubai Marina yet. At the last site inspection, in September 2026, it was 27% built. The developer is Select Global Development.
27%
Built, at the site inspection of 25 September 2026
- Finish at recent pace
- November 2038
- Construction started
- October 2024
- First registered
- April 2024
- Developer
- Select Global Development
- Community
- Dubai Marina
- Units
- 251
- Escrow bank
- Emirates NBD
- Name in Arabic
- سيكس سينسز رزيدنسز دبي مارينا
- Project number
- 3006
- Site inspections
- 3
Schedule
Since June 2026 Six Senses Residences Dubai Marina has added about 0.5 points a month. At that rate the site reaches 100% around November 2038. No completion date is on record to compare it with.
Site inspections
25 September 2026
27%+1.6 pts
18 June 2026
25%+3.7 pts
25 December 2024
21%
Context
Dubai Marina has 13 projects under construction, 46% built on average.
Select Global Development has 5 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Six Senses Residences Dubai Marina?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Six Senses Residences Dubai Marina handover date?
- No completion date is on record for Six Senses Residences Dubai Marina yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Six Senses Residences Dubai Marina?
- Six Senses Residences Dubai Marina was 27% built at the site inspection on 25 September 2026. The site has been inspected 3 times since December 2024. The Land Department took 22 site photos at its inspections.
- Who is building Six Senses Residences Dubai Marina?
- The registered developer is Select Global Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Six Senses Residences Dubai Marina?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Nautica OneAlso by Select Global Development. 85%.
- Nautica TwoAlso by Select Global Development. 85%.
- Artistry One ResidencesAlso by Select Global Development. 0%, Due February 2029.
- Artistry Two ResidencesAlso by Select Global Development. 0%, Due February 2029.
- Pier 8Nearby in Dubai Marina. 93%, Due March 2026, passed.
- Marina ShoresNearby in Dubai Marina. 87%, Due December 2026.
- Liv LuxNearby in Dubai Marina. 87%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.