Marina Cove construction progress
The registered completion date for Marina Cove in Dubai Marina is September 2029. At the last site inspection, in October 2026, it was 5.7% built. The developer is Emaar Development.
5.7%
Built, at the site inspection of 1 October 2026
Running behind its date
- Registered completion date
- September 2029
- Finish at recent pace
- October 2036
- Construction started
- October 2024
- First registered
- October 2024
- Developer
- Emaar Development
- Community
- Dubai Marina
- Units
- 227
- Escrow bank
- Emirates NBD
- Name in Arabic
- مارينا كوف
- Project number
- 3328
- Site inspections
- 3
Schedule
Between March 2026 and October 2026 the site added about 0.8 points a month. At that rate it would finish around October 2036, more than three months after its registered date of September 2029.
Site inspections
1 October 2026
5.7%+4.9 pts
25 March 2026
0.8%+0.8 pts
8 October 2024
0%
Context
Dubai Marina has 13 projects under construction, 46% built on average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Marina Cove?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Marina Cove handover date?
- The registered completion date is September 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Marina Cove?
- Marina Cove was 5.7% built at the site inspection on 1 October 2026. The site has been inspected 3 times since October 2024. The Land Department took 7 site photos at its inspections.
- Is Marina Cove delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
- Who is building Marina Cove?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for Marina Cove?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Pier 8Nearby in Dubai Marina. 93%, Due March 2026, passed.
- Marina ShoresNearby in Dubai Marina. 87%, Due December 2026.
- Liv LuxNearby in Dubai Marina. 87%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.