Skip to content

Marina Cove construction progress

Marina Cove in Dubai Marina is 5.7% built at the Land Department inspection of October 2026. Developer Emaar Development. Completion registered for September 2029.

5.7%

Built, at the Land Department site inspection of 1 October 2026

Running behind its date

Completion date (Land Department)
September 2029
Finish at recent pace
October 2036
Construction started
October 2024
Registered with the Land Department
October 2024
Community
Dubai Marina
Units
227
Escrow bank
Emirates NBD
Name in Arabic
مارينا كوف
Land Department project number
3328
Land Department site inspections
3

Schedule

Between March 2026 and October 2026 the site added about 0.8 points a month. At that rate it would finish around October 2036, more than three months after the September 2029 date registered with the Land Department.

0%25%50%75%100%20252026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 October 2026

5.7%+4.9 pts

  • Marina Cove construction site, Land Department inspection photo 1, 1 October 2026
  • Marina Cove construction site, Land Department inspection photo 2, 1 October 2026
  • Marina Cove construction site, Land Department inspection photo 3, 1 October 2026

25 March 2026

0.8%+0.8 pts

  • Marina Cove construction site, Land Department inspection photo 1, 25 March 2026
  • Marina Cove construction site, Land Department inspection photo 2, 25 March 2026

8 October 2024

0%

  • Marina Cove construction site, Land Department inspection photo 1, 8 October 2024
  • Marina Cove construction site, Land Department inspection photo 2, 8 October 2024

All 7 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 44% built on average. Marina Cove is behind that average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Marina Cove?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Marina Cove be completed?
The completion date registered with the Dubai Land Department is September 2029. At the pace of its recent inspections the site would reach 100% around October 2036. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Marina Cove is built?
5.7%, measured at the Land Department site inspection on 1 October 2026. The Land Department engineers have inspected the site 3 times since October 2024.
Is Marina Cove delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
Who is building Marina Cove?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for Marina Cove?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.