Rove Home Dubai Marina construction progress

Rove Home Dubai Marina in Dubai Marina is 7.8% built at the Land Department inspection of July 2026. Developer Irth Elite Development. Completion registered for March 2028.

7.8%

Built, at the Land Department site inspection of 6 July 2026

Running behind its date

Completion date (Land Department)
March 2028
Finish at recent pace
February 2044
Construction started
December 2024
Registered with the Land Department
November 2024
Developer
Irth Elite Development
Community
Dubai Marina
Units
682
Escrow bank
Commercial Bank of Dubai
Name in Arabic
روف منازل دبي مارينا
Land Department project number
3393
Land Department site inspections
6

Schedule

Between July 2025 and July 2026 the site added about 0.4 points a month. At that rate it would finish around February 2044, more than three months after the March 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 July 2026

7.8%+0.3 pts

  • Rove Home Dubai Marina construction site, Land Department inspection photo 1, 6 July 2026
  • Rove Home Dubai Marina construction site, Land Department inspection photo 2, 6 July 2026
  • Rove Home Dubai Marina construction site, Land Department inspection photo 3, 6 July 2026
  • Rove Home Dubai Marina construction site, Land Department inspection photo 4, 6 July 2026

23 March 2026

7.5%+0.3 pts

  • Rove Home Dubai Marina construction site, Land Department inspection photo 1, 23 March 2026
  • Rove Home Dubai Marina construction site, Land Department inspection photo 2, 23 March 2026
  • Rove Home Dubai Marina construction site, Land Department inspection photo 3, 23 March 2026
  • Rove Home Dubai Marina construction site, Land Department inspection photo 4, 23 March 2026

3 December 2025

7.1%+4.2 pts

  • Rove Home Dubai Marina construction site, Land Department inspection photo 1, 3 December 2025
  • Rove Home Dubai Marina construction site, Land Department inspection photo 2, 3 December 2025
  • Rove Home Dubai Marina construction site, Land Department inspection photo 3, 3 December 2025

30 July 2025

2.9%+2.8 pts

  • Rove Home Dubai Marina construction site, Land Department inspection photo 1, 30 July 2025
  • Rove Home Dubai Marina construction site, Land Department inspection photo 2, 30 July 2025
  • Rove Home Dubai Marina construction site, Land Department inspection photo 3, 30 July 2025
  • Rove Home Dubai Marina construction site, Land Department inspection photo 4, 30 July 2025

20 April 2025

0.1%+0.1 pts

  • Rove Home Dubai Marina construction site, Land Department inspection photo 1, 20 April 2025
  • Rove Home Dubai Marina construction site, Land Department inspection photo 2, 20 April 2025
  • Rove Home Dubai Marina construction site, Land Department inspection photo 3, 20 April 2025

8 November 2024

0%

  • Rove Home Dubai Marina construction site, Land Department inspection photo 1, 8 November 2024
  • Rove Home Dubai Marina construction site, Land Department inspection photo 2, 8 November 2024

All 22 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 44% built on average. Rove Home Dubai Marina is behind that average.

Own a unit in Rove Home Dubai Marina?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Rove Home Dubai Marina be completed?
The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around February 2044. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Rove Home Dubai Marina is built?
7.8%, measured at the Land Department site inspection on 6 July 2026. The Land Department engineers have inspected the site 6 times since November 2024.
Is Rove Home Dubai Marina delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Rove Home Dubai Marina?
The registered developer is Irth Elite Development.
Which bank holds the escrow account for Rove Home Dubai Marina?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.