Rove Home Dubai Marina construction progress
The registered completion date for Rove Home Dubai Marina in Dubai Marina is March 2028. At the last site inspection, in July 2026, it was 7.8% built. The developer is Irth Elite Development.
7.8%
Built, at the site inspection of 6 July 2026
Running behind its date
- Registered completion date
- March 2028
- Finish at recent pace
- February 2044
- Construction started
- December 2024
- First registered
- November 2024
- Developer
- Irth Elite Development
- Community
- Dubai Marina
- Units
- 682
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- روف منازل دبي مارينا
- Project number
- 3393
- Site inspections
- 6
Schedule
Between July 2025 and July 2026 the site added about 0.4 points a month. At that rate it would finish around February 2044, more than three months after its registered date of March 2028.
Site inspections
6 July 2026
7.8%+0.3 pts
23 March 2026
7.5%+0.3 pts
3 December 2025
7.1%+4.2 pts
30 July 2025
2.9%+2.8 pts
20 April 2025
0.1%+0.1 pts
8 November 2024
0%
Context
Dubai Marina has 13 projects under construction, 46% built on average.
Own a unit in Rove Home Dubai Marina?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Rove Home Dubai Marina handover date?
- The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2044. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Rove Home Dubai Marina?
- Rove Home Dubai Marina was 7.8% built at the site inspection on 6 July 2026. The site has been inspected 6 times since November 2024. The Land Department took 22 site photos at its inspections.
- Is Rove Home Dubai Marina delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building Rove Home Dubai Marina?
- The registered developer is Irth Elite Development.
- Which bank holds the escrow account for Rove Home Dubai Marina?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Pier 8Nearby in Dubai Marina. 93%, Due March 2026, passed.
- Marina ShoresNearby in Dubai Marina. 87%, Due December 2026.
- Liv LuxNearby in Dubai Marina. 87%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.