Liv Lux construction progress
Liv Lux in Dubai Marina is 79% built at the Land Department inspection of June 2026. Developer Marina Liv Development (Br Of Marina 2 Group Limited ) - Dubai Branch. Completion registered for December 2026.
79%
Built, at the Land Department site inspection of 2 June 2026
On pace for its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- December 2026
- Construction started
- November 2022
- Registered with the Land Department
- November 2022
- Developer
- Marina Liv Development (Br Of Marina 2 Group Limited ) - Dubai Branch
- Community
- Dubai Marina
- Units
- 229
- Escrow bank
- Emirates NBD
- Name in Arabic
- ليف لوكس
- Land Department project number
- 2502
- Land Department site inspections
- 10
Schedule
Since September 2025 Liv Lux has added about 3.2 points a month. That puts 100% around December 2026, within three months of its registered completion date of December 2026.
Site inspections
2 June 2026
79%+10 pts
12 January 2026
69%+17 pts
17 September 2025
52%+10 pts
14 May 2025
41%+6.8 pts
7 February 2025
35%+13 pts
14 October 2024
21%+5.1 pts
2 July 2024
16%+5.3 pts
13 March 2024
11%+7.9 pts
25 August 2023
3.1%+3.1 pts
8 November 2022
0%
Context
Dubai Marina has 13 projects under construction, 44% built on average.
Own a unit in Liv Lux?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Liv Lux be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around December 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Liv Lux is built?
- 79%, measured at the Land Department site inspection on 2 June 2026. The Land Department engineers have inspected the site 10 times since November 2022.
- Is Liv Lux delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
- Who is building Liv Lux?
- The registered developer is Marina Liv Development (Br Of Marina 2 Group Limited ) - Dubai Branch.
- Which bank holds the escrow account for Liv Lux?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Pier 8Nearby in Dubai Marina. 70%, Due March 2026, passed.
- Marina ShoresNearby in Dubai Marina. 87%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Aeternitas TowerNearby in Dubai Marina. 58%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.