Liv Lux construction progress

The registered completion date for Liv Lux in Dubai Marina is December 2026. At the last site inspection, in October 2026, it was 87% built. The developer is Marina Liv Development (Br Of Marina 2 Group Limited ) - Dubai Branch.

87%

Built, at the site inspection of 15 October 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
April 2027
Construction started
November 2022
First registered
November 2022
Developer
Marina Liv Development (Br Of Marina 2 Group Limited ) - Dubai Branch
Community
Dubai Marina
Units
229
Escrow bank
Emirates NBD
Name in Arabic
ليف لوكس
Project number
2502
Site inspections
11

Schedule

Between January 2026 and October 2026 the site added about 2.0 points a month. At that rate it would finish around April 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 October 2026

87%+8.2 pts

  • Liv Lux construction site, inspection photo 1, 15 October 2026
  • Liv Lux construction site, inspection photo 2, 15 October 2026
  • Liv Lux construction site, inspection photo 3, 15 October 2026
  • Liv Lux construction site, inspection photo 4, 15 October 2026

2 June 2026

79%+10 pts

  • Liv Lux construction site, inspection photo 1, 2 June 2026
  • Liv Lux construction site, inspection photo 2, 2 June 2026
  • Liv Lux construction site, inspection photo 3, 2 June 2026
  • Liv Lux construction site, inspection photo 4, 2 June 2026

12 January 2026

69%+17 pts

  • Liv Lux construction site, inspection photo 1, 12 January 2026
  • Liv Lux construction site, inspection photo 2, 12 January 2026
  • Liv Lux construction site, inspection photo 3, 12 January 2026
  • Liv Lux construction site, inspection photo 4, 12 January 2026

17 September 2025

52%+10 pts

  • Liv Lux construction site, inspection photo 1, 17 September 2025
  • Liv Lux construction site, inspection photo 2, 17 September 2025
  • Liv Lux construction site, inspection photo 3, 17 September 2025
  • Liv Lux construction site, inspection photo 4, 17 September 2025

14 May 2025

41%+6.8 pts

  • Liv Lux construction site, inspection photo 1, 14 May 2025
  • Liv Lux construction site, inspection photo 2, 14 May 2025
  • Liv Lux construction site, inspection photo 3, 14 May 2025
  • Liv Lux construction site, inspection photo 4, 14 May 2025

7 February 2025

35%+13 pts

  • Liv Lux construction site, inspection photo 1, 7 February 2025
  • Liv Lux construction site, inspection photo 2, 7 February 2025
  • Liv Lux construction site, inspection photo 3, 7 February 2025
  • Liv Lux construction site, inspection photo 4, 7 February 2025

14 October 2024

21%+5.1 pts

  • Liv Lux construction site, inspection photo 1, 14 October 2024
  • Liv Lux construction site, inspection photo 2, 14 October 2024
  • Liv Lux construction site, inspection photo 3, 14 October 2024
  • Liv Lux construction site, inspection photo 4, 14 October 2024

2 July 2024

16%+5.3 pts

  • Liv Lux construction site, inspection photo 1, 2 July 2024
  • Liv Lux construction site, inspection photo 2, 2 July 2024
  • Liv Lux construction site, inspection photo 3, 2 July 2024
  • Liv Lux construction site, inspection photo 4, 2 July 2024

13 March 2024

11%+7.9 pts

  • Liv Lux construction site, inspection photo 1, 13 March 2024
  • Liv Lux construction site, inspection photo 2, 13 March 2024
  • Liv Lux construction site, inspection photo 3, 13 March 2024
  • Liv Lux construction site, inspection photo 4, 13 March 2024

25 August 2023

3.1%+3.1 pts

  • Liv Lux construction site, inspection photo 1, 25 August 2023
  • Liv Lux construction site, inspection photo 2, 25 August 2023
  • Liv Lux construction site, inspection photo 3, 25 August 2023
  • Liv Lux construction site, inspection photo 4, 25 August 2023

All 81 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 46% built on average.

Own a unit in Liv Lux?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Liv Lux handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Liv Lux?
Liv Lux was 87% built at the site inspection on 15 October 2026. The site has been inspected 11 times since November 2022. The Land Department took 81 site photos at its inspections.
Is Liv Lux delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Liv Lux?
The registered developer is Marina Liv Development (Br Of Marina 2 Group Limited ) - Dubai Branch.
Which bank holds the escrow account for Liv Lux?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.