Liv Lux construction progress
The registered completion date for Liv Lux in Dubai Marina is December 2026. At the last site inspection, in October 2026, it was 87% built. The developer is Marina Liv Development (Br Of Marina 2 Group Limited ) - Dubai Branch.
87%
Built, at the site inspection of 15 October 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- April 2027
- Construction started
- November 2022
- First registered
- November 2022
- Developer
- Marina Liv Development (Br Of Marina 2 Group Limited ) - Dubai Branch
- Community
- Dubai Marina
- Units
- 229
- Escrow bank
- Emirates NBD
- Name in Arabic
- ليف لوكس
- Project number
- 2502
- Site inspections
- 11
Schedule
Between January 2026 and October 2026 the site added about 2.0 points a month. At that rate it would finish around April 2027, more than three months after its registered date of December 2026.
Site inspections
15 October 2026
87%+8.2 pts
2 June 2026
79%+10 pts
12 January 2026
69%+17 pts
17 September 2025
52%+10 pts
14 May 2025
41%+6.8 pts
7 February 2025
35%+13 pts
14 October 2024
21%+5.1 pts
2 July 2024
16%+5.3 pts
13 March 2024
11%+7.9 pts
25 August 2023
3.1%+3.1 pts
Context
Dubai Marina has 13 projects under construction, 46% built on average.
Own a unit in Liv Lux?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Liv Lux handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Liv Lux?
- Liv Lux was 87% built at the site inspection on 15 October 2026. The site has been inspected 11 times since November 2022. The Land Department took 81 site photos at its inspections.
- Is Liv Lux delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Liv Lux?
- The registered developer is Marina Liv Development (Br Of Marina 2 Group Limited ) - Dubai Branch.
- Which bank holds the escrow account for Liv Lux?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Pier 8Nearby in Dubai Marina. 93%, Due March 2026, passed.
- Marina ShoresNearby in Dubai Marina. 87%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Aeternitas TowerNearby in Dubai Marina. 58%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)














.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)