Aeternitas Tower construction progress

The registered completion date for Aeternitas Tower in Dubai Marina is December 2027. At the last site inspection, in September 2026, it was 58% built. The developer is London Gate Real Estate Development.

58%

Built, at the site inspection of 25 September 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
May 2029
Construction started
December 2023
First registered
December 2023
Community
Dubai Marina
Units
661
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
ايتيرنيتاس تاور
Project number
2797
Site inspections
7

Schedule

Between November 2025 and September 2026 the site added about 1.3 points a month. At that rate it would finish around May 2029, more than three months after its registered date of December 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 September 2026

58%+9.1 pts

  • Aeternitas Tower construction site, inspection photo 1, 25 September 2026
  • Aeternitas Tower construction site, inspection photo 2, 25 September 2026
  • Aeternitas Tower construction site, inspection photo 3, 25 September 2026
  • Aeternitas Tower construction site, inspection photo 4, 25 September 2026

12 March 2026

49%+4.1 pts

  • Aeternitas Tower construction site, inspection photo 1, 12 March 2026
  • Aeternitas Tower construction site, inspection photo 2, 12 March 2026
  • Aeternitas Tower construction site, inspection photo 3, 12 March 2026
  • Aeternitas Tower construction site, inspection photo 4, 12 March 2026

24 November 2025

45%+4.4 pts

  • Aeternitas Tower construction site, inspection photo 1, 24 November 2025
  • Aeternitas Tower construction site, inspection photo 2, 24 November 2025
  • Aeternitas Tower construction site, inspection photo 3, 24 November 2025
  • Aeternitas Tower construction site, inspection photo 4, 24 November 2025

30 July 2025

40%+4.0 pts

  • Aeternitas Tower construction site, inspection photo 1, 30 July 2025
  • Aeternitas Tower construction site, inspection photo 2, 30 July 2025
  • Aeternitas Tower construction site, inspection photo 3, 30 July 2025
  • Aeternitas Tower construction site, inspection photo 4, 30 July 2025

8 February 2025

36%+5.5 pts

  • Aeternitas Tower construction site, inspection photo 1, 8 February 2025
  • Aeternitas Tower construction site, inspection photo 2, 8 February 2025
  • Aeternitas Tower construction site, inspection photo 3, 8 February 2025
  • Aeternitas Tower construction site, inspection photo 4, 8 February 2025

18 October 2024

31%+6.9 pts

  • Aeternitas Tower construction site, inspection photo 1, 18 October 2024
  • Aeternitas Tower construction site, inspection photo 2, 18 October 2024
  • Aeternitas Tower construction site, inspection photo 3, 18 October 2024
  • Aeternitas Tower construction site, inspection photo 4, 18 October 2024

3 November 2023

24%

  • Aeternitas Tower construction site, inspection photo 1, 3 November 2023
  • Aeternitas Tower construction site, inspection photo 2, 3 November 2023
  • Aeternitas Tower construction site, inspection photo 3, 3 November 2023
  • Aeternitas Tower construction site, inspection photo 4, 3 November 2023

All 62 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 46% built on average.

London Gate Real Estate Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Aeternitas Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Aeternitas Tower handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Aeternitas Tower?
Aeternitas Tower was 58% built at the site inspection on 25 September 2026. The site has been inspected 7 times since November 2023. The Land Department took 62 site photos at its inspections.
Is Aeternitas Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Aeternitas Tower?
The registered developer is London Gate Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Aeternitas Tower?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.