Aeternitas Tower construction progress

Aeternitas Tower in Dubai Marina is 58% built at the Land Department inspection of September 2026. Developer London Gate Real Estate Development. Completion registered for December 2027.

58%

Built, at the Land Department site inspection of 25 September 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
May 2029
Construction started
December 2023
Registered with the Land Department
December 2023
Community
Dubai Marina
Units
661
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
ايتيرنيتاس تاور
Land Department project number
2797
Land Department site inspections
7

Schedule

Between November 2025 and September 2026 the site added about 1.3 points a month. At that rate it would finish around May 2029, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%2024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 September 2026

58%+9.1 pts

  • Aeternitas Tower construction site, Land Department inspection photo 1, 25 September 2026
  • Aeternitas Tower construction site, Land Department inspection photo 2, 25 September 2026
  • Aeternitas Tower construction site, Land Department inspection photo 3, 25 September 2026
  • Aeternitas Tower construction site, Land Department inspection photo 4, 25 September 2026

12 March 2026

49%+4.1 pts

  • Aeternitas Tower construction site, Land Department inspection photo 1, 12 March 2026
  • Aeternitas Tower construction site, Land Department inspection photo 2, 12 March 2026
  • Aeternitas Tower construction site, Land Department inspection photo 3, 12 March 2026
  • Aeternitas Tower construction site, Land Department inspection photo 4, 12 March 2026

24 November 2025

45%+4.4 pts

  • Aeternitas Tower construction site, Land Department inspection photo 1, 24 November 2025
  • Aeternitas Tower construction site, Land Department inspection photo 2, 24 November 2025
  • Aeternitas Tower construction site, Land Department inspection photo 3, 24 November 2025
  • Aeternitas Tower construction site, Land Department inspection photo 4, 24 November 2025

30 July 2025

40%+4.0 pts

  • Aeternitas Tower construction site, Land Department inspection photo 1, 30 July 2025
  • Aeternitas Tower construction site, Land Department inspection photo 2, 30 July 2025
  • Aeternitas Tower construction site, Land Department inspection photo 3, 30 July 2025
  • Aeternitas Tower construction site, Land Department inspection photo 4, 30 July 2025

8 February 2025

36%+5.5 pts

  • Aeternitas Tower construction site, Land Department inspection photo 1, 8 February 2025
  • Aeternitas Tower construction site, Land Department inspection photo 2, 8 February 2025
  • Aeternitas Tower construction site, Land Department inspection photo 3, 8 February 2025
  • Aeternitas Tower construction site, Land Department inspection photo 4, 8 February 2025

18 October 2024

31%+6.9 pts

  • Aeternitas Tower construction site, Land Department inspection photo 1, 18 October 2024
  • Aeternitas Tower construction site, Land Department inspection photo 2, 18 October 2024
  • Aeternitas Tower construction site, Land Department inspection photo 3, 18 October 2024
  • Aeternitas Tower construction site, Land Department inspection photo 4, 18 October 2024

3 November 2023

24%

  • Aeternitas Tower construction site, Land Department inspection photo 1, 3 November 2023
  • Aeternitas Tower construction site, Land Department inspection photo 2, 3 November 2023
  • Aeternitas Tower construction site, Land Department inspection photo 3, 3 November 2023
  • Aeternitas Tower construction site, Land Department inspection photo 4, 3 November 2023

All 62 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 44% built on average.

London Gate Real Estate Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Aeternitas Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Aeternitas Tower be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around May 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Aeternitas Tower is built?
58%, measured at the Land Department site inspection on 25 September 2026. The Land Department engineers have inspected the site 7 times since November 2023.
Is Aeternitas Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Aeternitas Tower?
The registered developer is London Gate Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Aeternitas Tower?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.