Aeternitas Tower construction progress
Aeternitas Tower in Dubai Marina is 58% built at the Land Department inspection of September 2026. Developer London Gate Real Estate Development. Completion registered for December 2027.
58%
Built, at the Land Department site inspection of 25 September 2026
Running behind its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- May 2029
- Construction started
- December 2023
- Registered with the Land Department
- December 2023
- Developer
- London Gate Real Estate Development
- Community
- Dubai Marina
- Units
- 661
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- ايتيرنيتاس تاور
- Land Department project number
- 2797
- Land Department site inspections
- 7
Schedule
Between November 2025 and September 2026 the site added about 1.3 points a month. At that rate it would finish around May 2029, more than three months after the December 2027 date registered with the Land Department.
Site inspections
25 September 2026
58%+9.1 pts
12 March 2026
49%+4.1 pts
24 November 2025
45%+4.4 pts
30 July 2025
40%+4.0 pts
8 February 2025
36%+5.5 pts
18 October 2024
31%+6.9 pts
3 November 2023
24%
Context
Dubai Marina has 13 projects under construction, 44% built on average.
London Gate Real Estate Development has 5 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Aeternitas Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Aeternitas Tower be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around May 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Aeternitas Tower is built?
- 58%, measured at the Land Department site inspection on 25 September 2026. The Land Department engineers have inspected the site 7 times since November 2023.
- Is Aeternitas Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Aeternitas Tower?
- The registered developer is London Gate Real Estate Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Aeternitas Tower?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Franck Muller VanguardAlso by London Gate Real Estate Development. 48%, Due November 2027.
- Lilian ResidencesAlso by London Gate Real Estate Development. 4.7%, Due April 2028.
- Mi Casa By London Gate Real Estate DevelopmentAlso by London Gate Real Estate Development. 19%, Due October 2028.
- Franck Muller YachtingAlso by London Gate Real Estate Development. 0%, Due July 2028.
- Pier 8Nearby in Dubai Marina. 70%, Due March 2026, passed.
- Marina ShoresNearby in Dubai Marina. 87%, Due December 2026.
- Liv LuxNearby in Dubai Marina. 79%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.