Skip to content

Bluewaters Bay construction progress

The registered completion date for Bluewaters Bay in Dubai Marina is March 2027. At the last site inspection, in August 2026, it was 37% built. The developer is Dhre 2 Bts.

37%

Built, at the site inspection of 25 August 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
March 2029
Construction started
February 2023
First registered
December 2022
Developer
Dhre 2 Bts
Community
Dubai Marina
Units
679
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بلوواترز باي
Project number
2530
Site inspections
11

Schedule

Between October 2025 and August 2026 the site added about 2.0 points a month. At that rate it would finish around March 2029, more than three months after its registered date of March 2027.

0%25%50%75%100%20232024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 August 2026

37%+8.6 pts

  • Bluewaters Bay construction site, inspection photo 1, 25 August 2026
  • Bluewaters Bay construction site, inspection photo 2, 25 August 2026
  • Bluewaters Bay construction site, inspection photo 3, 25 August 2026
  • Bluewaters Bay construction site, inspection photo 4, 25 August 2026

27 April 2026

28%+6.1 pts

  • Bluewaters Bay construction site, inspection photo 1, 27 April 2026
  • Bluewaters Bay construction site, inspection photo 2, 27 April 2026
  • Bluewaters Bay construction site, inspection photo 3, 27 April 2026
  • Bluewaters Bay construction site, inspection photo 4, 27 April 2026

26 January 2026

22%+6.7 pts

  • Bluewaters Bay construction site, inspection photo 1, 26 January 2026
  • Bluewaters Bay construction site, inspection photo 2, 26 January 2026
  • Bluewaters Bay construction site, inspection photo 3, 26 January 2026
  • Bluewaters Bay construction site, inspection photo 4, 26 January 2026

7 October 2025

16%+3.1 pts

  • Bluewaters Bay construction site, inspection photo 1, 7 October 2025
  • Bluewaters Bay construction site, inspection photo 2, 7 October 2025
  • Bluewaters Bay construction site, inspection photo 3, 7 October 2025
  • Bluewaters Bay construction site, inspection photo 4, 7 October 2025

7 July 2025

13%+2.1 pts

  • Bluewaters Bay construction site, inspection photo 1, 7 July 2025
  • Bluewaters Bay construction site, inspection photo 2, 7 July 2025
  • Bluewaters Bay construction site, inspection photo 3, 7 July 2025
  • Bluewaters Bay construction site, inspection photo 4, 7 July 2025

18 April 2025

10%+3.0 pts

  • Bluewaters Bay construction site, inspection photo 1, 18 April 2025
  • Bluewaters Bay construction site, inspection photo 2, 18 April 2025
  • Bluewaters Bay construction site, inspection photo 3, 18 April 2025
  • Bluewaters Bay construction site, inspection photo 4, 18 April 2025

16 January 2025

7.4%+5.4 pts

  • Bluewaters Bay construction site, inspection photo 1, 16 January 2025
  • Bluewaters Bay construction site, inspection photo 2, 16 January 2025
  • Bluewaters Bay construction site, inspection photo 3, 16 January 2025
  • Bluewaters Bay construction site, inspection photo 4, 16 January 2025

23 September 2024

2.0%+0.2 pts

  • Bluewaters Bay construction site, inspection photo 1, 23 September 2024
  • Bluewaters Bay construction site, inspection photo 2, 23 September 2024

21 March 2024

1.9%+0.9 pts

  • Bluewaters Bay construction site, inspection photo 1, 21 March 2024
  • Bluewaters Bay construction site, inspection photo 2, 21 March 2024

9 August 2023

0.9%+0.9 pts

  • Bluewaters Bay construction site, inspection photo 1, 9 August 2023
  • Bluewaters Bay construction site, inspection photo 2, 9 August 2023
  • Bluewaters Bay construction site, inspection photo 3, 9 August 2023
  • Bluewaters Bay construction site, inspection photo 4, 9 August 2023

All 70 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 46% built on average.

Dhre 2 Bts has 12 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Bluewaters Bay?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Bluewaters Bay handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Bluewaters Bay?
Bluewaters Bay was 37% built at the site inspection on 25 August 2026. The site has been inspected 11 times since November 2022. The Land Department took 70 site photos at its inspections.
Is Bluewaters Bay delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Bluewaters Bay?
The registered developer is Dhre 2 Bts. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Bluewaters Bay?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.