Bluewaters Bay construction progress

Bluewaters Bay in Dubai Marina is 37% built at the Land Department inspection of August 2026. Developer Dhre 2 Bts. Completion registered for March 2027.

37%

Built, at the Land Department site inspection of 25 August 2026

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
March 2029
Construction started
February 2023
Registered with the Land Department
December 2022
Developer
Dhre 2 Bts
Community
Dubai Marina
Units
679
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بلوواترز باي
Land Department project number
2530
Land Department site inspections
11

Schedule

Between October 2025 and August 2026 the site added about 2.0 points a month. At that rate it would finish around March 2029, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%20232024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 August 2026

37%+8.6 pts

  • Bluewaters Bay construction site, Land Department inspection photo 1, 25 August 2026
  • Bluewaters Bay construction site, Land Department inspection photo 2, 25 August 2026
  • Bluewaters Bay construction site, Land Department inspection photo 3, 25 August 2026
  • Bluewaters Bay construction site, Land Department inspection photo 4, 25 August 2026

27 April 2026

28%+6.1 pts

  • Bluewaters Bay construction site, Land Department inspection photo 1, 27 April 2026
  • Bluewaters Bay construction site, Land Department inspection photo 2, 27 April 2026
  • Bluewaters Bay construction site, Land Department inspection photo 3, 27 April 2026
  • Bluewaters Bay construction site, Land Department inspection photo 4, 27 April 2026

26 January 2026

22%+6.7 pts

  • Bluewaters Bay construction site, Land Department inspection photo 1, 26 January 2026
  • Bluewaters Bay construction site, Land Department inspection photo 2, 26 January 2026
  • Bluewaters Bay construction site, Land Department inspection photo 3, 26 January 2026
  • Bluewaters Bay construction site, Land Department inspection photo 4, 26 January 2026

7 October 2025

16%+3.1 pts

  • Bluewaters Bay construction site, Land Department inspection photo 1, 7 October 2025
  • Bluewaters Bay construction site, Land Department inspection photo 2, 7 October 2025
  • Bluewaters Bay construction site, Land Department inspection photo 3, 7 October 2025
  • Bluewaters Bay construction site, Land Department inspection photo 4, 7 October 2025

7 July 2025

13%+2.1 pts

  • Bluewaters Bay construction site, Land Department inspection photo 1, 7 July 2025
  • Bluewaters Bay construction site, Land Department inspection photo 2, 7 July 2025
  • Bluewaters Bay construction site, Land Department inspection photo 3, 7 July 2025
  • Bluewaters Bay construction site, Land Department inspection photo 4, 7 July 2025

18 April 2025

10%+3.0 pts

  • Bluewaters Bay construction site, Land Department inspection photo 1, 18 April 2025
  • Bluewaters Bay construction site, Land Department inspection photo 2, 18 April 2025
  • Bluewaters Bay construction site, Land Department inspection photo 3, 18 April 2025
  • Bluewaters Bay construction site, Land Department inspection photo 4, 18 April 2025

16 January 2025

7.4%+5.4 pts

  • Bluewaters Bay construction site, Land Department inspection photo 1, 16 January 2025
  • Bluewaters Bay construction site, Land Department inspection photo 2, 16 January 2025
  • Bluewaters Bay construction site, Land Department inspection photo 3, 16 January 2025
  • Bluewaters Bay construction site, Land Department inspection photo 4, 16 January 2025

23 September 2024

2.0%+0.2 pts

  • Bluewaters Bay construction site, Land Department inspection photo 1, 23 September 2024
  • Bluewaters Bay construction site, Land Department inspection photo 2, 23 September 2024

21 March 2024

1.9%+0.9 pts

  • Bluewaters Bay construction site, Land Department inspection photo 1, 21 March 2024
  • Bluewaters Bay construction site, Land Department inspection photo 2, 21 March 2024

9 August 2023

0.9%+0.9 pts

  • Bluewaters Bay construction site, Land Department inspection photo 1, 9 August 2023
  • Bluewaters Bay construction site, Land Department inspection photo 2, 9 August 2023
  • Bluewaters Bay construction site, Land Department inspection photo 3, 9 August 2023
  • Bluewaters Bay construction site, Land Department inspection photo 4, 9 August 2023

All 70 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 44% built on average.

Dhre 2 Bts has 11 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Bluewaters Bay?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Bluewaters Bay be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around March 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Bluewaters Bay is built?
37%, measured at the Land Department site inspection on 25 August 2026. The Land Department engineers have inspected the site 11 times since November 2022.
Is Bluewaters Bay delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Bluewaters Bay?
The registered developer is Dhre 2 Bts. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for Bluewaters Bay?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.