Greenview 2 construction progress

The register lists Greenview 2 in Dubai World Central as complete, with a registered completion date of January 2024. Its last site inspection on record was in September 2024. The developer is Emaar Dubai South Dwc.

100%

Built, at the site inspection of 5 September 2024

Construction complete

Registered completion date
January 2024
Construction started
October 2019
First registered
July 2019
Units
292
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جرين فيو 2
Project number
2172
Site inspections
10

Schedule

The register lists Greenview 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20202021202220232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 September 2024

100%+27 pts

  • Greenview 2 construction site, inspection photo 1, 5 September 2024
  • Greenview 2 construction site, inspection photo 2, 5 September 2024
  • Greenview 2 construction site, inspection photo 3, 5 September 2024
  • Greenview 2 construction site, inspection photo 4, 5 September 2024

11 December 2023

73%+23 pts

  • Greenview 2 construction site, inspection photo 1, 11 December 2023
  • Greenview 2 construction site, inspection photo 2, 11 December 2023
  • Greenview 2 construction site, inspection photo 3, 11 December 2023
  • Greenview 2 construction site, inspection photo 4, 11 December 2023

7 August 2023

50%+19 pts

  • Greenview 2 construction site, inspection photo 1, 7 August 2023
  • Greenview 2 construction site, inspection photo 2, 7 August 2023
  • Greenview 2 construction site, inspection photo 3, 7 August 2023
  • Greenview 2 construction site, inspection photo 4, 7 August 2023

13 April 2023

31%+18 pts

  • Greenview 2 construction site, inspection photo 1, 13 April 2023
  • Greenview 2 construction site, inspection photo 2, 13 April 2023
  • Greenview 2 construction site, inspection photo 3, 13 April 2023
  • Greenview 2 construction site, inspection photo 4, 13 April 2023

19 December 2022

13%+4.4 pts

  • Greenview 2 construction site, inspection photo 1, 19 December 2022
  • Greenview 2 construction site, inspection photo 2, 19 December 2022
  • Greenview 2 construction site, inspection photo 3, 19 December 2022
  • Greenview 2 construction site, inspection photo 4, 19 December 2022

30 August 2022

9.0%+1.9 pts

  • Greenview 2 construction site, inspection photo 1, 30 August 2022
  • Greenview 2 construction site, inspection photo 2, 30 August 2022
  • Greenview 2 construction site, inspection photo 3, 30 August 2022
  • Greenview 2 construction site, inspection photo 4, 30 August 2022

26 April 2022

7.1%+1.4 pts

  • Greenview 2 construction site, inspection photo 1, 26 April 2022
  • Greenview 2 construction site, inspection photo 2, 26 April 2022
  • Greenview 2 construction site, inspection photo 3, 26 April 2022
  • Greenview 2 construction site, inspection photo 4, 26 April 2022

31 May 2021

5.7%+3.2 pts

  • Greenview 2 construction site, inspection photo 1, 31 May 2021
  • Greenview 2 construction site, inspection photo 2, 31 May 2021
  • Greenview 2 construction site, inspection photo 3, 31 May 2021
  • Greenview 2 construction site, inspection photo 4, 31 May 2021

24 February 2021

2.5%+2.0 pts

  • Greenview 2 construction site, inspection photo 1, 24 February 2021
  • Greenview 2 construction site, inspection photo 2, 24 February 2021
  • Greenview 2 construction site, inspection photo 3, 24 February 2021
  • Greenview 2 construction site, inspection photo 4, 24 February 2021

18 February 2020

0.5%

  • Greenview 2 construction site, inspection photo 1, 18 February 2020
  • Greenview 2 construction site, inspection photo 2, 18 February 2020
  • Greenview 2 construction site, inspection photo 3, 18 February 2020
  • Greenview 2 construction site, inspection photo 4, 18 February 2020

All 69 site photos, by inspection date

Context

Dubai World Central has 53 projects under construction, 31% built on average.

Emaar Dubai South Dwc has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Greenview 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Greenview 2 handover date?
Construction of Greenview 2 is recorded as complete, with a registered completion date of January 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Greenview 2?
Greenview 2 was 100% built at the site inspection on 5 September 2024. The site has been inspected 10 times since February 2020. The Land Department took 69 site photos at its inspections.
Is Greenview 2 delayed?
The register lists construction as complete.
Who is building Greenview 2?
The registered developer is Emaar Dubai South Dwc. It has 23 other projects under construction in Dubai.
Which bank holds the escrow account for Greenview 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.