Greenview 2 construction photos

69 photos from 10 site inspections, newest first. The percentage is how much of Greenview 2 was built on the day of each visit.

5 September 2024100% built

11 December 202373% built

7 August 202350% built

13 April 202331% built

19 December 202213% built

30 August 20229.0% built

26 April 20227.1% built

31 May 20215.7% built

24 February 20212.5% built

18 February 20200.5% built

Back to Greenview 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.