Fairway Villas 2 construction photos

65 photos from 11 site inspections, newest first. The percentage is how much of Fairway Villas 2 was built on the day of each visit.

17 August 202692% built

7 July 202683% built

12 March 202668% built

20 November 202560% built

18 July 202546% built

25 April 202537% built

8 January 202518% built

30 September 20245.3% built

25 March 20240.6% built

28 September 20230.4% built

13 March 20230% built

Back to Fairway Villas 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.