Obj1 Real Estate Development projects under construction
Obj1 Real Estate Development has 14 projects under construction in Dubai. On average they are 22% built. 3 have passed their registered completion date. The next one due is Vivid Tower, in November 2026.
- Evergrin HouseJumeirah Garden City55%Due June 2026, passed
- Luminar Tower 1Jumeirah Village Triangle40%Due October 2026, passed
- Luminar Tower 2Jumeirah Village Triangle40%Due October 2026, passed
- Lridian Park 1Jumeirah Village Circle33%Due February 2027
- Verdania 1Dubai Land Residence Complex31%Due March 2027
- Evergrin House 424%Due January 2027
- Iridian Park 2Jumeirah Village Circle21%Due February 2027
- Verdania 2Dubai Land Residence Complex20%Due March 2027
- Luminar Tower 3Jumeirah Village Triangle18%Due March 2027
- Vivid TowerAl Barsha South Fifth12%Due November 2026
- Evergrin House 2Jumeirah Garden City10%Due December 2026
- Silviana Park Living2.7%Due March 2027
- Vistara House 2Al Furjan2.1%Due December 2027
- Verdania 40.7%Due June 2028
Questions
How many projects is Obj1 Real Estate Development building in Dubai?
14 projects are under construction, 22% built on average at the latest site inspections.
Which Obj1 Real Estate Development projects finish next?
By registered completion date: Vivid Tower (November 2026, 12% built), Evergrin House 2 (December 2026, 10% built) and Evergrin House 4 (January 2027, 24% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
Are any Obj1 Real Estate Development projects delayed?
3 of its 14 projects have passed the registered completion date, among them Evergrin House, Luminar Tower 1 and Luminar Tower 2. A project counts as late once its registered completion date has passed before it reaches 100%.
Where is Obj1 Real Estate Development building?
Its projects are in Jumeirah Village Triangle (3), Dubai Land Residence Complex (2) and Jumeirah Garden City (2), and 3 other communities.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.