Luminar Tower 2 construction progress
Luminar Tower 2 in Jumeirah Village Triangle was registered to complete in October 2026 and is still under construction. At the last site inspection, in October 2026, it was 40% built. The developer is Obj1 Real Estate Development.
40%
Built, at the site inspection of 28 October 2026
1 months past its registered completion date
- Registered completion date
- October 2026
- Finish at recent pace
- June 2029
- Construction started
- August 2024
- First registered
- October 2024
- Developer
- Obj1 Real Estate Development
- Community
- Jumeirah Village Triangle
- Units
- 168
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- لومينار تاور تو
- Project number
- 3298
- Site inspections
- 7
Schedule
Luminar Tower 2 was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 1.9 points a month. Kept at that rate, the site would reach 100% around June 2029.
Site inspections
28 October 2026
40%+9.3 pts
30 July 2026
31%+8.0 pts
28 April 2026
23%+2.9 pts
11 December 2025
20%+7.2 pts
8 July 2025
13%+6.2 pts
17 February 2025
6.4%+6.4 pts
18 September 2024
0%
Context
Jumeirah Village Triangle has 29 projects under construction, 27% built on average.
Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Luminar Tower 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Luminar Tower 2 handover date?
- The registered completion date was October 2026, and the register still lists Luminar Tower 2 as under construction. At the pace of its recent inspections the site would reach 100% around June 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Luminar Tower 2?
- Luminar Tower 2 was 40% built at the site inspection on 28 October 2026. The site has been inspected 7 times since September 2024. The Land Department took 34 site photos at its inspections.
- Is Luminar Tower 2 delayed?
- Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
- Who is building Luminar Tower 2?
- The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Luminar Tower 2?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Luminar Tower 1Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Evergrin HouseAlso by Obj1 Real Estate Development. 55%, Due June 2026, passed.
- Vivid TowerAlso by Obj1 Real Estate Development. 12%, Due November 2026.
- Luminar Tower 3Also by Obj1 Real Estate Development. 18%, Due March 2027.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Volga TowerNearby in Jumeirah Village Triangle. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)