Silviana Park Living construction progress

The registered completion date for Silviana Park Living is March 2027. At the last site inspection, in August 2026, it was 2.7% built. The developer is Obj1 Real Estate Development.

2.7%

Built, at the site inspection of 13 August 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
April 2054
Construction started
November 2025
First registered
December 2025
Units
83
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
سيلفيانا بارك ليفينغ
Project number
4216
Site inspections
3

Schedule

Between November 2025 and August 2026 the site added about 0.3 points a month. At that rate it would finish around April 2054, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 August 2026

2.7%+2.3 pts

  • Silviana Park Living construction site, inspection photo 1, 13 August 2026
  • Silviana Park Living construction site, inspection photo 2, 13 August 2026
  • Silviana Park Living construction site, inspection photo 3, 13 August 2026

27 April 2026

0.4%+0.4 pts

  • Silviana Park Living construction site, inspection photo 1, 27 April 2026
  • Silviana Park Living construction site, inspection photo 2, 27 April 2026
  • Silviana Park Living construction site, inspection photo 3, 27 April 2026

9 November 2025

0%

  • Silviana Park Living construction site, inspection photo 1, 9 November 2025
  • Silviana Park Living construction site, inspection photo 2, 9 November 2025

All 8 site photos, by inspection date

Context

Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Silviana Park Living?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Silviana Park Living handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2054. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Silviana Park Living?
Silviana Park Living was 2.7% built at the site inspection on 13 August 2026. The site has been inspected 3 times since November 2025. The Land Department took 8 site photos at its inspections.
Is Silviana Park Living delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Silviana Park Living?
The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Silviana Park Living?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.