Silviana Park Living construction progress
The registered completion date for Silviana Park Living is March 2027. At the last site inspection, in August 2026, it was 2.7% built. The developer is Obj1 Real Estate Development.
2.7%
Built, at the site inspection of 13 August 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- April 2054
- Construction started
- November 2025
- First registered
- December 2025
- Developer
- Obj1 Real Estate Development
- Units
- 83
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- سيلفيانا بارك ليفينغ
- Project number
- 4216
- Site inspections
- 3
Schedule
Between November 2025 and August 2026 the site added about 0.3 points a month. At that rate it would finish around April 2054, more than three months after its registered date of March 2027.
Site inspections
13 August 2026
2.7%+2.3 pts
27 April 2026
0.4%+0.4 pts
9 November 2025
0%
Context
Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Silviana Park Living?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Silviana Park Living handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2054. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Silviana Park Living?
- Silviana Park Living was 2.7% built at the site inspection on 13 August 2026. The site has been inspected 3 times since November 2025. The Land Department took 8 site photos at its inspections.
- Is Silviana Park Living delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Silviana Park Living?
- The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Silviana Park Living?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Luminar Tower 1Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Evergrin HouseAlso by Obj1 Real Estate Development. 55%, Due June 2026, passed.
- Luminar Tower 2Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Vivid TowerAlso by Obj1 Real Estate Development. 12%, Due November 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.