Iridian Park 2 construction progress
The registered completion date for Iridian Park 2 in Jumeirah Village Circle is February 2027. At the last site inspection, in July 2026, it was 21% built. The developer is Obj1 Real Estate Development.
21%
Built, at the site inspection of 31 July 2026
Running behind its date
- Registered completion date
- February 2027
- Finish at recent pace
- August 2030
- Construction started
- August 2025
- First registered
- June 2026
- Developer
- Obj1 Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 86
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- 2 اريديان بارك
- Project number
- 3765
- Site inspections
- 2
Schedule
Between June 2025 and July 2026 the site added about 1.6 points a month. At that rate it would finish around August 2030, more than three months after its registered date of February 2027.
Site inspections
31 July 2026
21%+21 pts
24 June 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Iridian Park 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Iridian Park 2 handover date?
- The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Iridian Park 2?
- Iridian Park 2 was 21% built at the site inspection on 31 July 2026. The site has been inspected 2 times since June 2025. The Land Department took 8 site photos at its inspections.
- Is Iridian Park 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
- Who is building Iridian Park 2?
- The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Iridian Park 2?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Luminar Tower 1Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Evergrin HouseAlso by Obj1 Real Estate Development. 55%, Due June 2026, passed.
- Luminar Tower 2Also by Obj1 Real Estate Development. 40%, Due October 2026, passed.
- Vivid TowerAlso by Obj1 Real Estate Development. 12%, Due November 2026.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.