Iridian Park 2 construction progress

The registered completion date for Iridian Park 2 in Jumeirah Village Circle is February 2027. At the last site inspection, in July 2026, it was 21% built. The developer is Obj1 Real Estate Development.

21%

Built, at the site inspection of 31 July 2026

Running behind its date

Registered completion date
February 2027
Finish at recent pace
August 2030
Construction started
August 2025
First registered
June 2026
Units
86
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
2 اريديان بارك
Project number
3765
Site inspections
2

Schedule

Between June 2025 and July 2026 the site added about 1.6 points a month. At that rate it would finish around August 2030, more than three months after its registered date of February 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

31 July 2026

21%+21 pts

  • Iridian Park 2 construction site, inspection photo 1, 31 July 2026
  • Iridian Park 2 construction site, inspection photo 2, 31 July 2026
  • Iridian Park 2 construction site, inspection photo 3, 31 July 2026
  • Iridian Park 2 construction site, inspection photo 4, 31 July 2026

24 June 2025

0%

  • Iridian Park 2 construction site, inspection photo 1, 24 June 2025
  • Iridian Park 2 construction site, inspection photo 2, 24 June 2025

All 8 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Iridian Park 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Iridian Park 2 handover date?
The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Iridian Park 2?
Iridian Park 2 was 21% built at the site inspection on 31 July 2026. The site has been inspected 2 times since June 2025. The Land Department took 8 site photos at its inspections.
Is Iridian Park 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Iridian Park 2?
The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Iridian Park 2?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.